Cover Letter
One-page summary stating the reason for the change, the requester, and the recommended action so reviewers see the essentials immediately.
A complete package reduces ambiguity, protects payment rights, and documents approvals that can prevent later disputes or delays. It creates an auditable record that supports invoicing, lien notices, and project accounting while clarifying schedule and cost impacts for all parties.
Change order packages are prepared and reviewed by parties directly affected by the change: contractors, subcontractors, project managers, architects, and owners.
Clear role assignment speeds review and establishes who must sign, approve, and carry change impacts into project schedules and budgets.
One-page summary stating the reason for the change, the requester, and the recommended action so reviewers see the essentials immediately.
Concise, numbered description of what will be added, removed, or modified; include references to drawings, specs, and contract sections for clarity.
Detailed line items for labor, materials, equipment, markups, and any allowances; show subtotal, tax, and total change amount for accounting.
State days added or reduced and the revised critical-path dates; note any acceleration costs or phasing implications if applicable.
Designate who must approve (owner, architect, contractor) and provide signature blocks with printed names, titles, and dates.
Include vendor quotes, revised drawings, photos, time sheets, and any permits or third-party approvals supporting the change.
| Field Validation | Require numeric formats and MM/DD/YYYY for dates to prevent entry errors. |
|---|---|
| Routing Order | Define signer sequence: contractor → owner → architect as needed. |
| Authentication | Choose email or SMS code authentication per project sensitivity. |
| Storage Location | Set destination folder in your document repository for executed packages. |
| Notification Rules | Enable automatic reminders and completion notices for stakeholders. |
Choose a platform that supports standard file types, audit trails, and the authentication level your contract requires.
Submit within 7 calendar days of change discovery
Allow 10 business days for owner/architect review
Change effective on last required signature date
Adjustments reflected in the next invoicing cycle
Retain executed package per retention policy
Initiator prepares and submits the change order package for review.
Project team verifies scope, pricing, and schedule impacts for accuracy.
Authorized parties sign and notarize if required; approvals recorded.
Finalized package distributed and stored in project and accounting records.
A small property developer needed remote approvals for tenant-fit changes
A mid-size contractor consolidated subcontractor quotes into a single package
The project manager often signs for operational acceptance and scope confirmation; ensure they are expressly authorized by company delegation of authority to bind the contractor.
The owner’s designated representative or contracting officer must sign to approve cost and schedule changes; verify signing authority to avoid later disputes.