Project Identification

Draw Request No.   Submitted on

Scope of Work

Provide a concise description of the portion of contract scope covered by this draw. This description will govern acceptance criteria for payment.

Draw Request Summary & Budget

Period Covered:   to  

Deliverables and Acceptance Criteria

List each deliverable included in this draw and the acceptance criteria that will be used to verify completion. Acceptance requires the client to sign off or issue a written acceptance within the contractual review period.

Milestones

Record scheduled milestones and status for this draw.

Percent Complete:   Completion Date:

Percent Complete:   Completion Date:

Percent Complete:   Completion Date:

Work Completed & Materials Stored

Supporting Documentation Checklist

Check all documents attached to support this draw request. Absence of required documents may delay payment.

  Progress Photos

  Subcontractor / Supplier Invoices

  Conditional Lien Waivers (or Unconditional if attached)

  Certified Payroll / Labor Reports

  Permits / Inspection Certificates

Change Orders

List approved or pending change orders that affect this draw. If pending, describe effect on schedule and payment.

Change Order Reference:   Amount:   Status:

Payment Terms & Instructions

Payments due under this draw shall follow the contract payment schedule. Payment is due net as defined in the contract unless otherwise agreed in writing. Late payments may be subject to interest as stipulated in the contract.

Certifications, Warranties and Legal Notices

The undersigned certifies, under penalty of contract liability, that: (a) the work described herein has been performed in accordance with the contract documents, applicable codes and permits; (b) all amounts due to subcontractors, suppliers and laborers for work covered by prior draws have been paid or will be paid from previous payments; (c) there are no liens, claims or encumbrances arising from work covered by this draw, except those disclosed in writing attached to this package; (d) materials represented as stored are stored in identified locations and are free of liens except as disclosed; and (e) the information and supporting documentation submitted with this draw are complete and accurate to the best of the signatory's knowledge.

The Service Provider agrees to indemnify and hold harmless the Client from claims arising from acts or omissions related to the scope covered by this draw, except to the extent caused by the Client's gross negligence or willful misconduct. Parties acknowledge that payment made in reliance on this draw does not constitute final acceptance of work and does not waive any contractual rights or remedies.

Confidentiality: The contents of this draw package, including supporting documents and cost breakdowns, are confidential between the parties and may not be disclosed to third parties except as required by law or as necessary to process payment, enforce contract rights, or obtain subcontractor releases.

Governing Law: This draw package and any dispute arising from it shall be governed by the substantive law specified in the underlying contract; absent a contract provision, the laws of the state of the project location govern.

Certification Acknowledgement:   I certify that the foregoing statements are true and that I am authorized to submit this draw.

Change Order Process & Dispute Resolution

All changes affecting cost or schedule must be processed through formal change orders. Disputes arising from this draw shall be handled according to the dispute resolution provisions of the contract; pending resolution, undisputed portions shall remain payable.

Client

Client Name:

By:

Date:

Service Provider

Service Provider Name:

By:

Date:

Enter text

What the Project Management Draw Package Is

A Project Management Draw Package is a bundled submission used to request progress payments from a lender, owner, or funder during a construction or capital project. It typically includes a draw request form, schedule of values, invoices, lien waivers, inspection reports, and documentation of completed work or stored materials that justify release of retained funds. The package creates a single, auditable record linking progress milestones to disbursement amounts and supporting documents for lender underwriting, owner review, or escrow disbursement.

Why a Complete Draw Package Matters

A complete draw package speeds payment, reduces review cycles, and lowers the risk of funding holds or disputes by giving reviewers the documentation they need to approve disbursements reliably and consistently.

Why a Complete Draw Package Matters

Who Prepares and Reviews Draw Packages

Clear role definitions and a standard submission checklist reduce back-and-forth and shorten the time from submission to funding.

  • General Contractors — Prepare consolidated invoices, schedule-of-values updates, change orders, retainage accounting, and lien waivers for each draw cycle.
  • Lenders / Escrow Agents — Review documentation for compliance with loan terms, fund disbursements, and verify inspections before releasing funds.
  • Project Owners / Developers — Verify milestone completion, review sampling of supporting documents, and authorize payment or request clarifications.

Core Components of a Professional Draw Package

A professional draw package groups the financial request with verifiable supporting records so reviewers can confirm work completed, costs incurred, and lien release status without follow-up.

Draw Request

A signed request that lists the draw amount, contract balance, retainage, and authorized payer details for the current pay period.

Schedule of Values

Line-item breakdown of contract elements with cumulative and current values to show how the requested amount maps to work completed.

Invoices & Receipts

Vendor and subcontractor invoices or receipts tied to the line items supporting the dollar amounts in the draw.

Lien Waivers

Conditional or unconditional waivers from payees confirming work billed has been paid or will be paid upon disbursement.

Inspection Reports

Third-party or owner inspection certificates and photos verifying physical completion of the referenced scope.

Change Orders

Approved contract amendments with cost and schedule impacts included or referenced in the current draw.

Essential Data Fields to Include

Project ID: Unique project identifier
Contractor Name: Legal entity name
Draw Period: Start and end dates
Requested Amount: Numeric value
Retainage: Amount or percentage
Signer Role: Authorized signer title

Step-by-Step: Completing a Draw Package

Follow a consistent sequence to minimize review time: verify quantities, assemble supporting invoices, collect waivers, confirm inspections, and submit to the authorized reviewer or lender portal.

  • 01
    Verify Quantities: Confirm percent complete against schedule-of-values.
  • 02
    Collect Invoices: Attach vendor/subcontractor invoices with matching references.
  • 03
    Obtain Waivers: Secure lien waivers for billed amounts.
  • 04
    Submit Package: Upload to lender or owner review portal.

How to Configure an Online Draw Submission Workflow

A standard digital workflow enforces required fields, routes approvals, and captures an audit trail for each draw submission.

Field Configuration
Required Fields Project ID, Draw Date, Amount, Signer
Approval Steps Contractor → PM → Lender/Owner
Authentication Email link or SMS code; use stronger methods for high-value draws
Document Retention Store signed package and audit trail for compliance

Where to Send a Completed Draw Package

Submit through the channel specified in the loan or owner contract—common destinations are lender portals, owner email, escrow agent systems, or integrated project management platforms.

  • Lender Portal: Upload package to the lender's secure submission portal for underwriting.
  • Owner / Developer: Send package to owner for project-level approval or comment.
  • Escrow Agent: Deliver package when funds are held in escrow for release.
  • PM Software: Attach to project record in the PM or ERP system for traceability.

Digital Delivery and Platform Requirements

Ensure the chosen platform can retain a tamper-evident copy and export a certificate of completion for lender records.

  • File Formats: PDF, DOCX, and image files supported
  • Integrations: Connectors for NetSuite, Salesforce, Procore, Google Workspace
  • Security: TLS encryption and detailed audit trail

Typical Timelines and Processing Expectations

Draw cycles and lender review times vary by contract; building a timeline for submission, inspection, and funding helps set expectations and cashflow planning.

Submission Window:

Submit per contract schedule, commonly monthly or at milestone completion.

Lender Review Time:

Allow 5–15 business days for documentation and inspection review.

Inspection Scheduling:

Schedule third-party or owner inspections before submission to avoid delays.

Funding Disbursement:

Expect 3–10 business days post-approval for funds to be released.

Document Archival:

Archive the signed package and audit trail immediately after funding.

Common Preparation Mistakes to Avoid

  • Missing or unsigned lien waivers that prevent lenders from clearing pay applications and withholding disbursements.
  • Incorrect schedule-of-values math or mismatched invoice amounts triggering lender audit flags and payment holds.
  • Unclear supporting documentation, such as undated photos or incomplete inspection reports, causing verification delays.
  • Submitting late or outside the agreed draw window, which can defer funding to the next cycle and strain cashflow.

Risks and Consequences of an Incomplete Package

Payment Delay: Funding holds or extended payment cycles
Mechanic’s Lien: Increased exposure if waivers are missing
Audit Findings: Repayment demands or withholding adjustments
Contract Disputes: Disagreements over scope or billed amounts
Regulatory Risk: Noncompliance with lender terms or escrow rules
Cashflow Strain: Operational impacts from delayed receivables

eSignature Pricing and Feature Comparison for Draw Package Workflows

Pricing varies by vendor and plan; compare per-user rates, bulk-send support, audit trail features, HIPAA readiness, and any envelope or session caps.

signNow DocuSign Adobe Sign PandaDoc HelloSign
Starting Price $8/user/mo $15/user/mo $14/user/mo $19/user/mo $15/user/mo
Free Trial 7-day free trial Varies by vendor Varies by vendor Varies by vendor Varies by vendor
Bulk Send Yes (Business Premium) Varies by plan Varies by plan Varies by plan Limited or add-on
Audit Trail Yes Yes Yes Yes Yes
HIPAA Compliant Yes (BAA available) Yes (BAA available) Yes (BAA available) Varies Varies
Envelope Cap No cap 100 envelopes/user/year limit Varies by plan Varies by plan Varies by plan

Frequently Asked Questions About Draw Packages

Common questions focus on signature validity, required attachments, authentication, and how digital tools affect lender acceptance and auditability.


Need help? Contact support

be ready to get more
Join over 28 million airSlate SignNow users