Project Management EV Charging Stations

This template is fully customizable. Edit the text, fill out the fields, and send it for signature. Give it a try!

Project Management EV Charging Stations

Project Identification

Scope of Work

This Statement of Work (SOW) sets forth the obligations of Service Provider to deliver EV charging station planning, procurement, site preparation, installation, commissioning and project management services at locations designated by Client. The work described below shall include all labor, materials, equipment, permits, testing, and documentation necessary for a fully operational system in accordance with accepted industry standards and applicable electrical and building codes.

Deliverables and Acceptance

Service Provider shall deliver the items listed below. Each deliverable must include required documentation and pass Client acceptance testing defined by the associated acceptance criteria. Client acceptance shall occur within the acceptance period specified for each deliverable or shall be deemed accepted if Client does not provide written rejection with specific deficiencies within the acceptance period.

Timeline and Milestones

Project schedule below represents the baseline timeline. Any adjustments to milestone dates shall be managed through the Change Order Process defined in this SOW.

Budget and Payment

Client shall pay Service Provider the fees set forth below in exchange for the services and deliverables. All fees are exclusive of taxes unless otherwise stated. Invoice terms and retainage provisions are described in the Payment Schedule.

Change Order Process

Any change to scope, schedule, deliverables, or price shall be authorized only by a written Change Order signed by both parties. Service Provider shall provide a written proposal describing the change, price adjustment, and schedule impact. Client shall approve or reject the Change Order in writing within ten (10) business days of receipt. Emergency changes required for safety or code compliance may proceed immediately and will be documented and charged as a Change Order thereafter.

Responsibilities, Assumptions, and Dependencies

Safety, Compliance and Permits

Service Provider shall comply with all applicable local, state and federal laws, electrical and building codes, and manufacturer installation requirements. Service Provider is responsible for obtaining and maintaining all permits and inspections unless otherwise agreed in writing. Client shall provide reasonable access to sites and any required approvals from landlords or authorities having jurisdiction.

Confidentiality

Each party agrees that Confidential Information of the other party received in connection with this SOW shall be held in confidence and not disclosed to third parties except as required for performance or by law. Confidential Information shall not include information that is publicly available, already known to the receiving party, independently developed, or rightfully received from a third party without restriction.

Intellectual Property and Deliverable Ownership

Unless otherwise agreed in writing, Service Provider grants Client a non-exclusive, perpetual license to use deliverables provided under this SOW for Client’s internal operations. Service Provider retains ownership of pre-existing intellectual property and tools. Custom deliverable ownership transfers to Client upon final payment, subject to Client’s compliance with payment and license terms.

Warranties, Liability and Indemnity

Service Provider warrants that services will be performed in a workmanlike manner and that installed equipment will be free from defects in workmanship for a period specified in the equipment manufacturer warranty. EXCEPT AS EXPRESSLY PROVIDED, SERVICE PROVIDER DISCLAIMS ALL OTHER WARRANTIES, EXPRESS OR IMPLIED. EACH PARTY'S AGGREGATE LIABILITY FOR DIRECT DAMAGES SHALL NOT EXCEED THE AMOUNT PAID UNDER THIS SOW WITHIN THE TWELVE (12) MONTHS PRECEDING THE CLAIM. NEITHER PARTY SHALL BE LIABLE FOR CONSEQUENTIAL, INDIRECT, OR PUNITIVE DAMAGES. Service Provider shall indemnify and hold Client harmless from claims arising from Service Provider’s negligence or willful misconduct.

Termination

Either party may terminate this SOW for material breach if the breaching party fails to cure the breach within thirty (30) days after written notice. Upon termination for convenience by Client, Client shall pay Service Provider for work performed, reasonable demobilization, and documented costs incurred up to the effective date of termination.

Force Majeure

Neither party shall be liable for delays or failures in performance caused by events beyond its reasonable control, including but not limited to acts of God, natural disasters, strikes, governmental actions, or supply chain interruptions. The affected party shall provide prompt notice and use commercially reasonable efforts to mitigate the impact.

Insurance

Service Provider shall maintain commercial general liability, workers' compensation, and automobile liability insurance with limits customary for the industry. Certificates evidencing insurance shall be provided to Client upon request.

Governing Law and Dispute Resolution

This SOW shall be governed by the laws of the jurisdiction set forth below. The parties agree to negotiate in good faith to resolve disputes. If unresolved, disputes shall first be submitted to non-binding mediation, followed by binding arbitration if mediation fails, unless the parties agree otherwise in writing.

Acceptance of Terms

By executing below, Client and Service Provider represent and warrant that they are authorized to enter into this SOW, that the information provided is accurate, and that execution of this SOW constitutes a binding obligation on the parties in accordance with its terms.

Client

Client Name:

By:

Date:

Service Provider

Service Provider Name:

By:

Date:

Enter text✕

What this Project Management EV Charging Stations document is for

A Project Management EV Charging Stations document is a structured project plan and contract package used to coordinate site assessment, permitting, procurement, installation, testing, and handover for electric vehicle charging infrastructure. It centralizes scope, milestones, responsibilities, budgets, technical specifications, and acceptance criteria so owners, contractors, utilities, and permitting authorities share a common record. The file can include schedules, permits, interconnection applications, contractor scopes, and risk registers and is commonly routed for signatures, approvals, and regulatory filings during the life of the installation.

Why a formal project management package matters for EV charging

A single, consistent document reduces coordination errors, supports permit review, establishes contractual responsibilities, and creates an auditable trail for payments and regulatory compliance. It also streamlines vendor onboarding and enables faster approvals when signed and shared electronically under ESIGN/UETA frameworks.

Why a formal project management package matters for EV charging

Primary teams and stakeholders who rely on this document

This package is used by both public and private stakeholders during planning, permitting, and construction of EV charging sites.

  • Project managers coordinating schedule, budget, and vendor assignments across stakeholders.
  • Electrical contractors and installers documenting scope, site diagrams, and acceptance testing.
  • Property owners or fleet managers tracking costs, warranties, and charging performance requirements.

Each stakeholder group uses the document for different purposes: permitting evidence, contract enforcement, technical acceptance, or audit trail for incentives and utility interconnection.

Core sections to include in a professional EV charging project package

Include clear, standalone sections so reviewers can find technical and contractual details quickly; emphasize permit and interconnection requirements.

Scope of Work

Detailed tasks, deliverables, exclusions, and acceptance criteria including charger models, quantities, and site layout drawings.

Schedule

Milestones for procurement, permitting, electrical upgrades, installation, testing, and commissioning with responsible parties and durations.

Budget & Payments

Itemized cost estimates, payment schedule, retainage, change order process, and invoicing requirements tied to milestones.

Permits & Approvals

List of required local permits, interconnection forms, utility approvals, inspection steps, and expected lead times.

Technical Specs

Electrical load calculations, meter and distribution details, grounding, signage, ADA access, and environmental constraints.

Testing & Handover

Commissioning procedures, acceptance tests, documentation to deliver, training sessions, and warranty start dates.

Step-by-step: completing and circulating the project package

Follow these steps in order to prepare, approve, and archive the EV charging project documents efficiently.

  • 01
    Assemble Documents: Compile specs, drawings, permits, and interconnection forms.
  • 02
    Populate Fields: Complete required fields and attach supporting files.
  • 03
    Route for Review: Send to stakeholders for comments and redlines.
  • 04
    Sign and Archive: Obtain signatures, save final copies, and record audit trail.

Recommended digital workflow settings for online completion

Configure the e-signature workflow to match approval order, authentication level, and required documents for permitting and utility applications.

Field Configuration
Signer Order Sequential or parallel routing based on approvals.
Authentication Email link plus SMS code or KBA for higher assurance.
Conditional Fields Show permit-specific fields when permit type selected.
Integrations Map attachments to PM/ERP or cloud storage systems.

Where to send the completed package

After final review and signatures, distribute the package to all parties and record locations required by regulators, utilities, and owners.

  • Local Permit Office: Upload or deliver required permit application copies.
  • Utility Interconnection: Submit interconnection forms and one-line diagrams.
  • Owner / Fleet: Provide final as-built and warranty documents.
  • Project Archive: Store signed package in records management system.

Digital signing and distribution: technical considerations

Choose tools that produce a clear audit trail, support required file formats, and integrate with your project management systems.

  • File Formats: PDF, DOCX accepted
  • Integrations: Salesforce, NetSuite, Google Workspace
  • Authentication: Email, SMS, KBA options

Typical permit and project timing to plan for

Timelines vary by jurisdiction and utility; use these common checkpoints to build an internal schedule and avoid approval delays.

Permit Submission Lead Time:

Submit 2–8 weeks before planned installation depending on jurisdiction.

Utility Interconnection Review:

Allow 4–12 weeks for study and approvals.

Procurement Lead Time:

Charger and transformer delivery commonly 6–16 weeks.

Installation Window:

Typical install for a small lot: 1–3 weeks of onsite work.

Commissioning and Testing:

Schedule 1–3 days per site for acceptance tests.

Key milestones for an EV charging station project

Track these sequential stages from planning through handover to maintain visibility and meet regulatory timelines.

01

Site Assessment

Confirm load capacity and site constraints early.

02

Permitting

Obtain local building and electrical permits.

03

Installation

Execute civil and electrical work on schedule.

04

Commissioning

Complete testing and provide signed acceptance documents.

Common mistakes to avoid when preparing the package

  • Incomplete electrical load calculations that omit diversity factors, causing utility delays and redesign costs.
  • Using inconsistent names or entity types across contract, permit, and interconnection forms, which can trigger rejections.
  • Failing to attach required utility forms or site drawings, resulting in permit or interconnection hold-ups.
  • Not collecting signatures in the correct order or at the required authentication level for regulator or owner acceptance.

Risks and potential consequences of errors or omissions

Permit Denial: Project delays and rework costs.
Utility Delay: Connection hold and revenue loss.
Contract Disputes: Payment disputes and claims.
Warranty Voids: Improper installation impacts coverage.
Regulatory Fines: Civil penalties for infractions.
Data Exposure: PII leaks can trigger legal obligations.

Essential sensitive information to protect in the project file

Site Location: Exact address and GPS coordinates
Owner PII: Names, emails, phone numbers
Utility Account: Account numbers and service IDs
Financials: Contract values and payment terms
Technical Plans: As-built drawings and electrical diagrams
Access Credentials: Keys, gates, or network login info

Practical examples of signed project workflows

Real organizations use e-signature and centralized project packages to reduce turnaround and maintain compliance across distributed stakeholders.

Optica Ventures — COO

As a small developer, the team needed simple, reliable signing for partners and tenants.

  • Rapid external signing reduced coordination time.
  • "The interface is simple and easy-to-use for our team; more importantly, it is just as easy for our customers."

Martin Properties — Founder

A real estate operator used centralized signed packages to handle multiple property rollouts.

  • Consistent templates cut review cycles.
  • "I can process and execute all of these documents online with 100% compliance and built-in security. Whether on mobile or working offline, I can get forms back to their necessary parties efficiently."

eSignature vendor comparison for project documents (signNow first)

Vendor pricing and basic feature availability to consider when selecting an eSignature provider for EV charging project workflows.

signNow DocuSign Adobe Sign PandaDoc HelloSign
Starting Price $8/user/mo $15/user/mo $14/user/mo $19/user/mo $15/user/mo
Free Trial Yes — 7-day free trial Varies by vendor Varies by vendor Varies by vendor Varies by vendor
Bulk Send Yes (Premium plan) Yes Yes Yes Yes
Audit Trail Yes Yes Yes Yes Yes
HIPAA Compliant Yes Yes Yes No No
Envelope Cap No cap 100 envelopes/user/year Varies Varies Varies

Frequently asked questions about using this project package

Answers to common questions about e-signing, notarization, and ensuring the document is enforceable for EV charging projects.


Need help? Contact support

be ready to get more
Join over 28 million airSlate SignNow users