Request Header
Include project name, contract number, request date, and requestor contact information so the form can be indexed and routed without additional clarification.
A consistent extension form reduces ambiguity by capturing the cause, scope, and approvals in one place, supporting contract compliance and auditability. It helps avoid informal email promises that are difficult to validate and provides a clear record for schedule recovery, invoicing, and dispute resolution.
Completed forms serve as an enforceable record for progress reporting, change control, and invoice or liquidated-damages calculations when properly countersigned.
The Senior Project Manager prepares the extension request, assesses schedule and budget impact, and submits supporting evidence. Their narrative should explain root causes, mitigation steps, and an achievable revised FAT date to enable informed approvals and minimize downstream claims.
The Contractor Representative provides factual support for the delay—resource constraints, delivery delays, or technical blockers—and supplies revised delivery timelines, cost estimates if applicable, and acceptance of any conditional requirements set by the client.
Include project name, contract number, request date, and requestor contact information so the form can be indexed and routed without additional clarification.
Describe root causes with specific dates and vendor references. Include any corrective actions already taken and the likelihood of recurrence to inform risk decisions.
Quantify schedule shifts, cost implications, affected deliverables, and resource changes. Use concise tables when multiple milestones are affected to aid review.
Provide the requested FAT date, intermediate checkpoints, and contingency plan including resource commitments and testing windows to support acceptance.
List required approvers and their role (owner, QA lead, contract manager). Include signature blocks and date fields to capture formal acceptance.
Attach logs, vendor notices, test reports, and photos where relevant. Well-labeled evidence shortens review time and reduces follow-up questions.
| Field | Configuration |
|---|---|
| Upload Document | PDF or DOCX accepted |
| Assign Signers | Role-based order |
| Authentication | Email or SMS code |
| Notifications | Automated reminders enabled |
Confirm recipients can open attachments and receive authentication codes; ensure your eSignature provider captures an auditable certificate of completion.
Submit before original FAT date
Approver acknowledges within 5 business days
Approval or denial within 10 business days
New FAT date becomes effective on approval
Notify affected parties within 2 business days
Requestor files form with attachments and evidence.
Project and QA teams assess feasibility and impacts.
Owner or contract manager approves, rejects, or conditions extension.
Schedule updated and stakeholders informed; execute mitigation plan.
| Criteria | FAT Extension | Contract Amendment |
|---|---|---|
| Purpose | schedule relief | contract terms change |
| Formality | lower formality | higher formality |
| Signatures | approvers only | parties and counsel |
| When used | short delays | material contractual changes |
| signNow | DocuSign | Adobe Sign | PandaDoc | HelloSign | |
|---|---|---|---|---|---|
| Starting Price | $8/user/mo | $15/user/mo | $14/user/mo | $19/user/mo | $15/user/mo |
| Free Trial | 7-day trial | Varies | Varies | Varies | Varies |
| Bulk Send | Yes | Yes | Yes | Yes | No |
| Audit Trail | Yes | Yes | Yes | Yes | Yes |
| HIPAA Compliant | Yes | Yes | Yes | No | No |
| Envelope Cap | No cap | 100 envelopes/user/year | Varies | Varies | Varies |
A small developer documented a failed third-party delivery affecting FAT timelines
An enterprise operations team used a templated extension to manage vendor delays