STATEMENT OF WORK AND KEY PERFORMANCE PARAMETERS HANDBOOK

Guidance for Capital Asset Acquisition Projects

Office of Acquisition and Project Management

U.S. Department of Energy

Washington, DC

September 30, 2014

FOREWORD

This handbook was developed by the Department of Energy (DOE) Office of Acquisition and Project Management (OAPM) for use on DOE capital asset projects by federal project directors (FPDs) and contractors. It provides suggested guidance and best practices for developing a complete statement of work (SOW) in support of contracts for capital asset projects, and the development of key performance parameters (KPPs) for capital asset projects within DOE.

This handbook is not a requirements document. It is intended to provide a consistent approach based on best practices to support the development of comprehensive and effective SOWs and KPPs for capital asset projects. DOE programs could further issue more specific/applicable guidance tailored to their particular needs. DOE programs may also use alternate methodologies or tailored approaches more suitable to their projects and technologies, as appropriate.

This handbook will be revised or augmented periodically with pertinent data that may be useful in improving its utility.

SECTION 1.0: INTRODUCTION

1.1 Overview

The execution of capital asset projects within the originally approved scope, cost and schedule baseline remains a priority within the Department of Energy (DOE). Achieving this objective for capital asset projects under the DOE acquisition contract process requires clear and concise statements of work (SOWs) and robust key performance parameters (KPPs).

1.2 Background

The SOW describes in clear, understandable terms the work to be done in developing or producing the products to be delivered or services to be performed by a contractor. KPPs define a characteristic, function, requirement or design basis that, if changed, would have a major impact on the system or facility performance, schedule, cost and/or risk for the project.

1.4 Scope and Objective

This handbook is limited to providing guidance only for developing SOWs and KPPs for DOE capital asset projects. It focuses on how to develop SOWs and KPPs to help ensure that project scope is defined in a manner that permits accurate assessment of project performance.

SECTION 2.0: STATEMENT OF WORK DEVELOPMENT

2.1 Purpose of Statement of Work

The purpose of an SOW is to provide a formal narrative description of products or services to be supplied by a contractor based on mission need.

2.2 Defining the Statement of Work

A good SOW exhibits the following characteristics:

  • Clear and concise high level definition of scope of work to be performed.
  • Defines performance requirements in measurable, mission-related terms.
  • Descriptive and not prescriptive; results-oriented.
  • Becomes a standard for measuring contractor performance.
  • Limits the opportunities for contractor scope creep.

2.2.1 Relationship between Statement of Work and Specification

The SOW defines all work performance requirements for the contractual effort. Technical specifications are typically referenced in the SOW.

2.2.2 Relationship between Statement of Work and Work Breakdown Structure (WBS) Alignment

The WBS is a direct representation of the work scope defined in the SOW and is an essential element of an Earned Value Management System (EVMS).

2.2.3 Relationship between Statement of Work and Contract

The level of detail, clarity, and identification of performance objectives and expectations in the SOW contribute to contract pricing structure and administration.

2.3 SOW Written Format

A good SOW should try to include the following sections:

  • SOW Section Title
  • Scope
  • Applicable Documents
  • Requirements

2.4 SOW Development Approach

A systematic process is essential to SOW development. The team should ensure that only those tasks which add value to the product are included in the SOW.

SECTION 3.0: KEY PERFORMANCE PARAMETER DEVELOPMENT

3.1 Purpose of a Key Performance Parameter

The purpose of a KPP is to establish a measurable benchmark for completing project scope.

3.2 Defining a Key Performance Parameter

KPPs embody the critical attributes of a project mission and are finalized at CD-2.

3.3 Identifying Key Performance Parameter Characteristics

The quality of a good KPP can be measured by the SMART test:

  • Specific
  • Measurable
  • Attainable
  • Realistic
  • Timely

3.4 Establishing Key Performance Parameter Values

KPPs should state the desired objective value and the associated minimum threshold value succinctly and in quantitative terms, if possible.

3.5 Determining the Appropriate Number and Specificity of Key Performance Parameters

The total number of KPPs should be the minimum number needed to characterize the major drivers of project performance.

3.6 Key Performance Parameters and Critical Decisions

KPPs are key elements in the critical decision process and are inherent in establishing the initial PB and subsequent changes thereto.

SECTION 4.0: KPP DOCUMENTATION AND CHANGE CONTROL

4.1 Overview

KPPs are integral to the PB approved at CD-2 and adjustments after CD-2 may have significant impact to the project TPC, scope and schedule.

4.2 Documentation of Key Performance Parameters

KPPs are documented in the PEP and project data sheets (PDSs), and are captured in the Project Assessment Reporting System (PARS II).

4.3 Revising Key Performance Parameters

A BCP is required for any change to a project that affects its ability to satisfy the mission need or does not meet the approved PB.

APPENDIX A: KEY PERFORMANCE PARAMETERS EXAMPLES

Facility Construction (e.g., office building)

KPP #1. The facility will be a 3-story Class A office building providing 250,000 sf of usable space.

KPP #2. The facility will provide a Class A office building that meets the minimum certification requirements for LEED.

KPP #3. Provide a facility that includes a cafeteria of a minimum of 12,000 sf.

Processing Operation (e.g., nuclear construction)

KPP #1. Include high-bay area that includes 50% open space to accommodate additional equipment in the future.

KPP #2. Provide a processing capability of at least 5 gpm.

KPP #3. Provide above-ground storage capacity of 50,000 gallons of feedstock.

KPP #4. All gloveboxes will be designed and fabricated to NQA-1 standards.

KPP #5. The reactor will be capable of attaining 1400 °F within 12 hours.

APPENDIX B: ACRONYMS

AE - acquisition executive

BCP - baseline change control

CD - critical decisions

DOE - U.S. Department of Energy

EVMS - earned value management system

FAR - Federal Acquisition Regulation

FPD - federal project director

IPT - integrated project team

KPP - key performance parameter

PARS - Project Assessment Reporting System

PB - performance baseline

PDS - project data sheet

PEP - project execution plan

PPEP - preliminary project execution plan

PWS - Performance Work Statement

RLS - resource-loaded schedule

SOW - statement of work

TPC - total project cost

WBS - work breakdown structure

APPENDIX C: REFERENCES

GAO Cost Estimating and Assessment Guide – Best Practices for Developing and Managing Capital Program Costs.

DOE O 413.3B, Program and Project Management for the Acquisition of Capital Asset Projects.

DOE G 413.3-5A, US Department of Energy Performance Baseline Guide.

Work Breakdown Structure Handbook, US Department of Energy.

Document Information

Form Fields

Project Name:

Project Location:

Federal Project Director:

Contractor Name:

Effective Date:

Completion Date:

Scope Summary

Requirements Summary

Applicable Documents

KPP Objective

KPP Threshold

Include LEED Certification

Include Contractor Management Reserve

Include DOE Contingency

Include Performance Baseline

Signature

Authorized Signature

Date

Enter text✕

What the Handbook Is and when it applies

The Statement of Work and Key Performance Parameters Handbook for Capital Asset Projects is a standardized procurement and project management document that defines scope, deliverables, performance metrics, acceptance criteria, and reporting requirements for capital asset projects. It combines a formal Statement of Work (SOW) with measurable Key Performance Parameters (KPPs) to align stakeholders, contractors, and oversight bodies during planning, execution, and closeout. The Handbook provides templates, definitions, and instructions for drafting contract language, assigning responsibilities, and establishing verification methods to support compliance with federal procurement standards and internal agency governance.

Why adopt the Handbook for capital asset work

Use the Handbook to create clear, measurable contractual requirements that reduce disputes, improve performance monitoring, and streamline acceptance of capital assets. It standardizes performance language, supports auditability, and helps agencies meet schedule, budget, and regulatory objectives through defined metrics and verification steps.

Why adopt the Handbook for capital asset work

Typical roles that prepare or rely on the Handbook

Typical users include contracting officers, program managers, engineers, procurement specialists, and contractor points of contact responsible for capital asset delivery.

  • Federal contracting officers and program managers coordinating scope, KPPs, acceptance, and oversight.
  • Prime contractors and subcontractors defining deliverables, testing, and verification methods in proposals and contracts.
  • Technical leads, quality assurance teams, and asset custodians tracking performance and corrective actions.

Stakeholders across finance, legal, and facilities groups also reference the Handbook for budgeting, contract review, and lifecycle planning.

Core components to include in each Handbook

Core components in the Handbook organize project scope, performance metrics, verification methods, testing protocols, acceptance criteria, roles, and reporting to ensure consistent capital asset delivery.

Scope Definition

Precise project boundaries, included and excluded work, deliverables, and interfaces. Defines tangible outputs and acceptance thresholds to prevent scope creep and provide objective measures for contractor performance and invoicing.

Performance Metrics

Quantified Key Performance Parameters (KPPs), thresholds, measurement frequency, and data sources for each metric. Specifies instrumentation, sampling methods, acceptable variance, reporting cadence, and escalation triggers for out-of-compliance performance.

Verification Methods

Testing procedures, witness points, independent verification and validation (IV&V) roles, and acceptance tests that demonstrate compliance with KPPs before final acceptance and payment milestones and recordkeeping requirements.

Acceptance Criteria

Objective pass/fail criteria, sample sizes, allowable deviations, and signoff authority. Ties successful delivery to milestone payments and specifies remedial steps for failed acceptance tests including re-test scheduling.

Roles & Responsibilities

Defines contracting officer, program manager, contractor, quality assurance, and subcontractor duties, decision authorities, and reporting lines to clarify accountability across procurement and project execution and escalation paths for disputes.

Reporting & Records

Required deliverables, format, frequency, retention periods, data custody, and audit trail expectations for compliance reviews, contract audits, and post-project performance assessments, including schedule of records and electronic submission formats.

Step-by-step process to complete and approve the Handbook

Follow these sequential steps to draft, review, route, and finalize the Handbook for a capital asset procurement.

  • 01
    Draft SOW: Populate scope, deliverables, and KPPs in template.
  • 02
    Define Tests: Specify acceptance tests and measurement methods.
  • 03
    Internal Review: Legal, procurement, and technical reviews complete.
  • 04
    Execute Contract: Signatures, notarization if required, and distribution.

How Handbook drafts move from upload to archived record

This workflow shows how the Handbook moves from drafting to verified acceptance and record retention.

  • Upload Template: Place the filled template in contract repository.
  • Assign Reviewers: Add legal, technical, and procurement approvers.
  • Conduct Testing: Perform IV&V and document results.
  • Closeout & Archive: Capture final acceptance and retention metadata.

Recommended digital workflow settings for Handbook use

Recommended digital workflow settings support version control, role-based routing, conditional fields, and audit trails for the Handbook.

Field Configuration
Version Control Enable versioning and track changes
Role Routing Set sequential approvers and conditional branches
Conditional Fields Show fields based on prior answers
Audit Trail Record timestamps, IP, and user actions

Technical requirements for eSubmission and eSignature

Use platforms that support PDF and DOCX, role-based routing, single-sign-on, audit trails, and conditional fields to enable secure eSubmission and version control.

  • File Formats: PDF, DOCX, and Excel supported
  • Integrations: Salesforce, NetSuite, Google Workspace
  • Auth Methods: Email, SMS, SSO, KBA options

Key dates to track when using the Handbook

Key deadlines and submission dates affect procurement milestones, acceptance testing, and financial closeout; track them in project schedule and contract annexes.

Target SOW Draft Completion Date:

Complete draft before procurement solicitation and internal reviews.

KPP Establishment and Approval Deadline:

Set KPPs prior to testing and baseline acceptance.

Acceptance Test Schedule Finalization Date:

Finalize test plans, sample sizes, and witness lists.

Contract Execution and Signatures Due:

Signatures trigger obligations, payments, and retention start dates.

Final Closeout Report and Records Submission Date:

Submit final deliverables, test results, and retention inventory.

Consequences of incorrect or incomplete Handbooks

Payment Withholding: Incorrect acceptance can delay payments
Scope Disputes: Ambiguous scope leads to change orders
Regulatory Noncompliance: Violations risk audits and penalties
Schedule Overruns: Poor KPPs cause delays and cost growth
Contract Termination: Material breaches may lead to termination
Recordkeeping Failures: Insufficient records hinder audits and claims

Security and compliance expectations for Handbook data

Encryption In Transit: Use TLS 1.2 or TLS 1.3
Encryption At Rest: AES-256 encryption for stored documents
Audit Trail: Capture timestamps, IPs, and actions
Access Controls: Role-based access and SSO
Compliance Frameworks: SOC 2, ISO 27001, PCI, HIPAA
BAA Availability: HIPAA BAA offered on request

eSignature vendor pricing and feature snapshot for Handbook workflows

Comparison of eSignature pricing and core features to inform platform selection for Handbook eSubmission, focusing on cost, bulk send support, audit trails, and HIPAA availability.

signNow DocuSign Adobe Sign PandaDoc HelloSign
Starting Price $8/user/mo $15/user/mo $14/user/mo $19/user/mo $15/user/mo
Free Trial 7-day free trial Varies Varies Varies Varies
Bulk Send Yes Yes Yes Yes No
Audit Trail Yes Yes Yes Yes Yes
HIPAA Compliant Yes Yes Yes No No

Illustrative examples of Handbook use in practice

These real-world examples show how organizations use standardized SOW and KPP templates to speed approvals, reduce disputes, and document acceptance.

Optica Ventures

Optica Ventures used the Handbook templates and eSignature workflows to standardize contractor deliverables and acceptance across multiple redevelopment sites.

  • Reduced turnaround on acceptance documentation.
  • Their COO noted the interface simplified internal approvals and made it easier for external contractors to submit certified test results, improving audit readiness while shortening the time between inspection, acceptance, and payment.

Martin Properties

Martin Properties applied the Handbook to leasehold asset projects, aligning testing criteria and documentation for property improvements and tenant deliverables.

  • Enabled 100% compliance and mobile execution.
  • The founder reported the ability to complete and execute documents online with built-in security reduced site visits and administrative delay; project closeout cycles shortened and records were retained for audit purposes.

Frequently asked questions about completing and enforcing the Handbook