Memorandum Page 1 of 11 M E M O R A N D U M TO:Illinois Contractors and SubcontractorsRE:Critical documents to be executed and critical Dates to be observed with respect to every job. __________________________________________________________________ INTRODUCTION This Memorandum is put forth to Illinois General Contractors and Subcontractors to
make them aware of actions that must be taken and deadlines that must be observed to in
order to ensure the preservation of their rights to payment.This Memorandum will point out general factors affecting the right to payment, set forth
time limits to be observed, provide Checklists to be used as jobs progress and, finally,
provide a timetable for easy reference which can be incorporated into the construction
schedule for each job. Ofcourse, this Memorandum is not a substitute for legal
consultation. Rather, it is a guide that should be put into practice and used to create lead
times for reporting payment problems to your attorney's office. GENERAL FACTORS AFFECTING MECHANICS LIENS Under Illinois law, a party to a written or oral contract can pursue its legal rights to
payment by filing a lawsuit for breach of contract. In addition, if the written or oral
contract is for construction work, a General Contractor or Subcontractor will also have
the right to seek payment by filing, and suing to foreclose on, a mechanics lien. This
right is granted under the Illinois Mechanics Lien Act for work on private property
(“Private Lien Act”) and the Illinois Liens Against Public Funds Act for work on public
property (“Public Lien Act”). In order to have the right to enforce a mechanics lien, the requirements for filing and
enforcement must be strictly followed in all respects. The most important of these
requirements are the absolute deadlines specified in both the Private Lien Act and the
Public Lien Act for the filing of a Notice of Lien and the subsequent suit to foreclose. Failure to adhere to the respective statutory deadlines is absolutely fatal to the right of a
General Contractor or Subcontractor to collect by means of enforcing it mechanics lien.
As a result, the General Contractor or Subcontractor will be forced to seek payment by
means of a breach of contract lawsuit, which will undoubtedly be less compelling on the
non-paying party since it may drag on for several years. Therefore, it is absolutely critical
that the specified time requirements are met.
Memorandum Page 2 of 11 The procedure for perfecting a mechanics lien differs for General Contractors,
Subcontractors and Materials Suppliers. In addition, those procedures vary based on the
type of property which is the subject of the work, as well as the type of customer for
whom the work is being done. CHANGE ORDER PROCEEDURES EXTRAS SHOULD NOT BE PERFORMED WITHOUT A WRITTEN CHANGE
ORDER THAT COMPLIES WITH THE FIVE REQUIREMENTS BELOW.A recurring issue for both General Contractors and Subcontractors is the right to payment
for “extras” performed at the job that were not in the original construction contract.
Illinois law requires that five (5) factors be present in order for a General Contractor or
Subcontractor to be entitled to payment for the performance of “extras”:(a)The extras must be outside the scope of the original contract;(b)The extras must have been ordered by the Owner;(c)The Owner must agree to pay for the extras, either by words or conduct;(d)The extras must not have been volunteered by the General Contractor or
Subcontractor; and(e)The extras must not have been necessary to correct nonconforming work
of the General Contractor or Subcontractor.Failure to obtain written Change Orders will bar the right of the General Contractor or
Subcontractor to collect for extras. DATES TO BE OBSERVED General Contractor’s Mechanics Lien Private Property FILING A LIEN AND BRINGING SUIT WITHIN THE 4-MONTH PERIOD
MAXIMIZES THE RIGHTS OF THE GENERAL CONTRACTOR. IF THE 4-MONTH
PERIOD HAS LAPSED, A CLAIM SHOULD BE FILED AND A SUIT BROUGHT
TO ENFORCE THE CLAIM WITHIN THE 2-YEAR PERIOD.When a General Contractor performs work on private property, the primary contract runs
between the General Contractor and the owner of the private property (“Owner) or the
agent for the Owner, such as a tenant or lessee. The law of contract and Private Lien Act
control the General Contractor’s right to payment. To begin preserving its mechanics
lien rights, the General Contractor must file a General Contractor’s Notice of Mechanics
Lien Claim (“Mechanics Lien”) with the Recorder of Deeds of the County in which the
subject property is located.
Memorandum Page 3 of 11 FILING A MECHANICS LIEN CLAIM AND SUING TO ENFORCE LIEN RIGHTS
WITHIN THE 4-MONTH PERIOD ENTITLES THE GENERAL CONTRACTOR TO
RIGHTS WHICH ARE SUPERIOR TO THOSE OF MOST OTHER CREDITORS.4-Month Period: This period applies to either filing of a Mechanics Lien by the General
Contractor or commencement of an action by the General Contractor to enforce its
Mechanics Lien rights. The General Contractor has four (4) months after the Completion
Date to file its Mechanics Lien or file suit against the Owner to enforce its lien rights. By
doing so, the General Contractor assures superiority of its claim over all other parties
who may claim an interest in the subject property, including mortgagee institutions,
creditors of the owner, subsequent lien claimants and subsequent purchasers of the
property. Note that filing the Mechanics Lien is preferable to simply bringing suit, since
filing will preserve the rights of the General Contractor in case of a mortgage foreclosure. FILING A MECHANICS LIEN CLAIM AND SUING TO ENFORCE LIEN RIGHTS
WITHIN THE 2-YEAR PERIOD ENTITLES THE GENERAL CONTRACTOR TO
RIGHTS SUPERIOR TO THOSE OF THE OWNER.2-Year Period: This period applies to both the filing of a Mechanics Lien and the filing
of suit to enforce that Mechanics Lien. To be entitled to any recovery under the
Private Lien Act, the General Contractor must file its Mechanics Lien and bring a
suit to foreclose within two (2) years of the completion of the project (“Completion
Date”). Note that the Completion Date is the one on which the General Contractor
rendered its final services at the subject property.
In the alternative, the General Contractor may choose not to file its Mechanics Lien at all
and instead simply bring suit within the 2-Year Period. While doing so will still allow
the General Contractor to proceed against the Owner for payment, it will not give the
General Contractor’s claim superiority over the rights of mortgagee institutions,
subsequent buyers of the property or other parties having a claim against the property,
even if they have actual notice of the General Contractor’s claim. Public Property GENERAL CONTRACTOR THAT PERFORMS WORK ON PUBLIC PROPERTY
MAY NOT FILE A NOTICE OF MECHANICS LIEN OR SUIT TO ENFORCE SAME
AGAINST THE STATE OR POLITICAL SUBDIVISION FOR WHICH THE WORK
WAS DONE. INSTEAD, GENERAL CONTRACTOR MUST BRING A LAWSUIT
AGAINST THE GOVERNMENT ENTITY FOR WHOM THE WORK WAS DONE.When a General Contractor performs work on public property, the primary contract runs
between the General Contractor and the political subdivision that administers the
property for the public. There is no “owner” for the property per se, but rather an
obligation that runs from that government entity to the General Contractor. Under these
circumstances, the General Contractor is entitled to payment out of monies set aside by
Memorandum Page 4 of 11 the government entity for the project (“Bond”). The law of contract applies to the
General Contractor’s right to payment. The Illinois Liens Against Public Funds Act
(“Act”) does not permit the General Contractor to file a Mechanics Lien against the
public property. Instead, the General Contractor will bring suit for an accounting and for
the value of its Bond due to the default of the government entity. Subcontractor’s Mechanics Lien Private Property THE SUBCONTRACTOR MUST GIVE NOTICE TO THE OWNER OF THE
PROPERTY PRIOR TO BRINGING ITS MECHANICS LIEN. A MECHANICS LIEN
MUST BE FILED THEREAFTER WITHIN THE 4-MONTH OR 2-YEAR PERIODS
AS SET FORTH ABOVE FOR GENERAL CONTRACTORS.When a Subcontractor performs work for a General Contractor engaged in improvements
to private property, the primary contract runs between the Subcontractor and the General
Contractor, with the underlying contract for the work running from the General
Contractor to the Owner. The law of contract and the Private Lien Act apply to the
Subcontractor’s right to payment. To enforce its lien rights, the Subcontractor must give
written notice to the Owner indicating that the Subcontractor has been working at the
Property and is unpaid. The Subcontractor may then file a Subcontractor’s Notice of
Mechanics Lien Claim (“Mechanics Lien”) with the Recorder of Deeds of the County in
which the subject property is located. THE SUBCONTRACTOR MUST GIVE 90-DAY NOTICE IN WRITING PRIOR TO
BRINGING A MECHANICS LIEN AGAINST ANY PROPERTY.90-Day Notice: This form of notice must be given no matter what kind of private
property the Subcontractor is working on. The Subcontractor must give written notice to
the Owner, the Owner’s agent or the Architect, as well as any known lenders, within
ninety (90) days of the Completion Date, setting forth: (i) the amount due or to become
due for unpaid work; (ii) name of the Owner(s) and the lender, if known; (iii) name of the
General Contractor; (iv) name of the Subcontractor; (v) what the contract was for; (vi)
what was done or to be done, or what the claim is for; and (vii) a description of the
premises, such as by legal description. The 90-Day Notice must be dated and signed, but need not be made under oath. The
Owner, agent or Architect, and lenders on whom 90-Day Notice must be served are those
as of the date of the giving of notice – even if those parties have changed since the date of
the initial contract. The 90-Day Notice must be served personally or by registered or
certified mail, return receipt requested, delivery limited to addressee(s) only. If a
husband and wife occupy the premises then the 90-Day Notice must be served on both.
Memorandum Page 5 of 11 Exceptions to the 90-Day Notice rule do exist however, in situations where: (a) the
property in question is listed under the Torrens registration system; (b) the Owner, its
agent and the Architect reside in a county other than the one in which the premises are
located; (c) the Owner, its agent and the Architect cannot be found after a diligent search;
or (d) the Subcontractor’s claim is included in the General Contractor’s statement to the
Owner. Where the Owners, its agent and the Architect do not reside in the County in which the
property is located or cannot after a diligent search be found, the Subcontractor’s filing of
a Mechanics Lien in the office of the County Recorder is sufficient to satisfy the 90-Day
Notice requirement. However, the Mechanics Lien must state that the above parties have
not been found after a diligent search or do not reside in the County in which the property
is located.Under the last scenario, in which the Subcontractor’s work has been included in a Sworn
Statement from the General Contractor to the Owner, the Subcontractor is limited to the
amount listed as an unpaid claim in the General Contractor’s statement. Moreover, the
amount that the Subcontractor can collect will be limited to that amount which is listed in
the Sworn Statement and no greater recovery against the Owner will be allowed.IN ADDITION TO GIVING WRITTEN 90-DAY NOTICE, THE SUBCONTRACTOR
MUST GIVE WRITTEN 60-DAY NOTICE PRIOR TO BRINGING A MECHANICS
LIEN AGAINST AN OWNER OCCUPIED SINGLE FAMILY RESIDENCE. THE
PRIOR RULE REQUIRING 14-DAY NOTICE IS HEREBY REVOKED.60-Day Notice: This form of notice must be given, in addition to 90-Day Notice, by the
Subcontractor who performs work at an existing single family, owner occupied residence.
The Subcontractor must give written notice to the Owner within sixty (60) days of
starting work setting forth: (i) the name and address of the Subcontractor; (ii) the date on
which the Subcontractor began work; (iii) the type of work done or to be done; (iv) the
name of the General Contractor who requested the work; and (v) the following warning,
in at least 10-point, bold face type: NOTICE TO OWNER THE SUBCONTRACTOR PROVIDING THIS NOTICE HAS PERFORMED
WORK FOR OR DELIVERED MATERIAL TO YOUR HOME
IMPROVEMENT CONTRACTOR. THESE SERVICES OR MATERIALS ARE
BEING USED IN THE IMPROVEMENTS TO YOUR RESIDENCE AND
ENTITLE THE SUBCONTRACTOR TO FILE A LIEN AGAINST YOUR
RESIDENCE IF THE SERVICES OR MATERIALS ARE NOT PAID FOR BY
YOUR HOME IMPROVEMENT CONTRACTOR. A LIEN WAIVER WILL BE
PROVIDED TO YOUR CONTRACTOR WHEN THE SUBCONTRACTOR IS
PAID, AND YOU ARE URGED TO REQUEST THIS WAIVER FROM YOUR
CONTRACTOR WHEN PAYING FOR YOUR HOME IMPROVEMENTS.
Memorandum Page 6 of 11 The 60-Day Notice must be served on the Owner(s) personally or by certified mail, return
receipt requested, and if a husband and wife occupy the premises then the 60-Day Notice
must be served on both. Notice by Certified Mail is deemed to be complete as of the time
of mailing. The 60-Day Notice need not be signed, dated or be made under oath.Failure to serve the 60-Day Notice is not fatal to the Subcontractor’s claim for lien.
However, late notice will prevent the Subcontractor from collecting any sums
already paid by the Owner to the General Contractor on the Subcontractor’s
account, as in response to a General Contractor’s Sworn Statement. Public Property THE PUBLIC LIEN ACT IS THE SUBCONTRACTOR’S SOLE REMEDY FOR
WORK DONE AND MATERIALS SUPPLIED TO PUBLIC PROPERTY.When a Subcontractor performs work for a General Contractor engaged in improvements
to public property, the primary contract runs between the General Contractor and the
political subdivision that administers the subject property for the public benefit. Thus,
there is no owner of the subject property per se. Rather, a Subcontractor is entitled to the
payment of any monies set aside by the government entity for the project (“Bond”) under
the law of contract and the Public Lien Act apply to the right of the Subcontractor for
payment. The Act is the Subcontractor’s sole statutory remedy when performing
improvements to public property. State Agencies WHEN PERFORMING IMPROVEMENTS TO PUBLIC PROPERTY
ADMINISTERED BY A STATE AGENCY, THE SUBCONTRACTOR MUST GIVE
NOTICE WITHIN 30 DAYS OF DATE OF COMPLETION AND BRING SUIT
WITHIN 90 DAYS OF DATE OF COMPLETION TO PRESERVE ITS LIEN RIGHTS.In order to perfect is lien rights with respect to projects for a State agency such as a
department, board, commission, or any other person financing and constructing a public
improvement for the benefit of the State or department, board or commission thereof, the
Subcontractor must do the following:(a) send written notice of the Subcontractor’s claim for lien within thirty (30)
days of the completion of work or the date on which the claim arises, but
before money is paid to the General Contractor, to the official or officials
whose duty it would be to pay the original contractor (or in the alternative
file suit within that time); (b) by registered or certified mail, return receipt requested with delivery
limited to addressee only, or by delivery of written notice by personal
service;
Memorandum Page 7 of 11 (c) with a copy of that notice delivered to the contractor by one of the same
two methods; and (d) bring suit against the contractor for an accounting within ninety (90) days
of the notice date.Like the Mechanics Lien Act, the requirements of the Act are strictly construed. The lien would not be on the improved property itself, since a lien by a private party on a
public improvement would be considered void as against public policy, but rather against
the funds due to the General Contractor by the particular political entity. If proper notice
is given, the official responsible for paying the Subcontractor must withhold the claimed
funds until a resolution of the dispute or running of the time for suit. Note that filing a
Mechanics Lien with the Recorder of Deeds does not comply with the notice
requirements of the Act. Political Subdivisions of the State WHEN PERFORMING IMPROVEMENTS TO PROPERTY ADMINISTERED BY A
COUNTY, CITY, TOWNSHIP, VILLAGE OR OTHER MUNICIPALITY, THE
SUBCONTRACTOR MUST GIVE NOTICE WITHIN 30 DAYS OF DATE OF
COMPLETION AND BRING SUIT WITHIN 90 DAYS OF DATE OF COMPLETION
IN ORDER TO PRESERVE ITS LIEN RIGHTS.The steps that need to be taken by the Subcontractor to enforce and perfect its
Mechanics Lien are functionally the same as the procedures set forth above. With
respect to projects for any political subdivision of the State such as a county, a city, a
township, a village or other municipality, in order to perfect its lien rights the
Subcontractor must: (a) send written notice of the Subcontractor’s claim for lien within thirty (30)
days of the completion of work or the date on which the claim arises, but
before money is paid to the General Contractor, to the official or officials
whose duty it would be to pay the original contractor (or in the alternative
file suit within that time); (b) by registered or certified mail, return receipt requested with delivery limited to addressee only, or by delivery of written notice by personal
service; (c) with a copy of that notice delivered to the contractor by one of the same
two methods; and (d) bring suit against the contractor for an accounting within ninety (90) days
of the notice date.
Memorandum Page 8 of 11 Like the Mechanics Lien Act, the requirements of the Act are strictly construed. The lien would not be on the improved property itself, since a lien by a private party on a
public improvement would be considered void as against public policy, but rather against
the funds due to the General Contractor by the particular political entity. If proper notice
is given, the official responsible for paying the Subcontractor must withhold the claimed
funds until a resolution of the dispute or running of the time for suit. Note that filing a
Mechanics Lien with the Recorder of Deeds does not comply with the notice
requirements of the Act.
Memorandum Page 9 of 11 GENERAL CONTRACTOR’S CHECKLIST A General Contractor should make sure that the following points are followed on every
job:(1) A full Title Search should be obtained on the subject property to ensure that the
“owner” with whom the General Contractor is the proper contracting party. The
Title Search should also reveal the proper legal description of the subject
property, the presence of any pre-existing liens, the names of mortgagee
institutions, and other matters that affect title. This information will come in hand
later if disputes arise as to payment and a Mechanics Lien must be filed.(2) The Contract and all of its Exhibits should be reviewed by the General
Contractor’s Attorneys to ensure that it does not contain overly restrictive
covenants or conditions, such as a waiver of lien, default provisions, a confession
of judgment provision or similar language.(3) The General Contractor should identify Construction Lenders on the project and
give them written notice of its participation, inturn requesting written
acknowledgment from each lender that the General Contractor is on the job.(4) Sworn Statements should always be used by the General Contractor indicating
that all of its Subcontractors will be paid out of the proceeds paid by the Owner.
The General Contractor should require countersignature by the Owner on all
Sworn Statements prior to progressing to the next stage of the project.(5)In order to accurately prepare Sworn Statements, the General Contractor should
keep Daily Records of materials furnished and work performed on a project, and
should require that Subcontractors and, if appropriate, Materialmen do the same
and turn those records in regularly.(6) Lien Waivers should be gathered from all Subcontractors and Materialmen and
given to the Owner only as to those portions of the project paid for by the Owner
pursuant to Sworn Statements.(7) Only Written Change Orders should be honored by the General Contractor, and
then only those containing the Owner’s signature, the price for the alteration, and
notice that additional materials and labor will be involved.
Memorandum Page 10 of 11 SUBCONTRACTOR’S CHECKLIST A Subcontractor should make sure that the following points are followed on every job:(1)A full Title Search should be obtained on the subject property to ensure that the
“owner” with whom the General Contractor is the proper contracting party. The
Title Search should also reveal the proper legal description of the subject
property, the presence of any pre-existing liens, the names of mortgagee
institutions, and other matters that affect title. This information will come in hand
later if disputes arise as to payment and a Mechanics Lien must be filed,
especially since the Subcontractor’s Mechanics Lien rights are derivative of the
lien rights of the General Contractor. In other words, if the Owner of the subject
property has not been correctly identified, the Subcontractor risks sacrificing its
Mechanics Lien rights entirely.(2)The Contract between the General Contractor and the owner with all Exhibits
should be reviewed by the Subcontractor’s Attorneys to ensure that the
Subcontractor’s agreement with the General Contractor does not deviate
significantly from that Contract or contain overly restrictive provisions such as
those set out above.(3) The Subcontractor should identify Construction Lenders on the project and give
them written notice of its participation, inturn requesting written acknowledgment
from each lender that the Subcontractor is on the job.(4)The General Contractor’s Sworn Statements should always be reviewed by the
Subcontractor to verify that the Subcontractor has been, or will be, paid from the
proceeds remitted to the General Contractor by the Owner. (5)In order to substantiate its contributions to Sworn Statements, the Subcontractor
should keep Daily Records of materials furnished and work performed on a
project, and should require that Subsubcontractors and Materialmen do the same
and turn those records in regularly.(6) Lien Waivers should be only be delivered to the General Contractor as to those
portions of the project which have been accounted for in the General Contractor’s
Sworn Statement to the Owner.(7)Only Written Change Orders should be honored by the Subcontractor, and then
only those which contain the Owner’s signature, the price for the alteration, and
notice that additional materials and labor will be involved.
Memorandum Page 11 of 11 CONTRACTSTARTSTART PLUSCOMPLETE PLUS 90PLUS 4PLUS 2DATEDATE60 DAYSDATEDAYSMONTHSYEARSGENERAL1.Review the Contract and all Exhibits2.Title Search3.Identify Owner and Lenders4.Determine type of property1.Start keeping daily records2.Extras only
pursuant to written Change Orders3.Use Sworn
Statements for payment4. Lien Waivers only after payment1.Prepare any final punchlists2.Turn in Sworn Statements for final payout3.If any amounts unpaid, note in recordsLast day to file a Mechanics Lien or file Suit with
MAX priority,
including mortgagee banks and other creditors.Last day to file a Mechanics Lien or, if one has
already been filed, last day to sue to foreclose. Filed Liens not sued on lose their
effect at this time.SUB1.Review the Contract and all Exhibits2.Title Search3.Identify Owner and Lenders4.Determine type of property5.Start keeping daily records6.Extras only
pursuant to written Change Orders7.Use Sworn
Statements for payment8. Lien Waivers only after paymentOwners of owner- occupied, single-family homes must receive 60- Day Notice.4.Prepare any final punchlists5.Turn in Sworn Statements for final payout6.If any amounts unpaid, note in records90-Day Notice must be filed with
Recorder of County in which Property is located and sent
to the Owner, Agent or ArchitectLast day to file a Mechanics Lien or file Suit with
MAX priority,
including mortgagee banks and other creditors.Last day to file a Mechanics Lien or, if one has
already been filed, last day to sue to foreclose. Filed Liens not sued on lose their
effect at this time.