4470.2 REV-1
CHAPTER 4. COMPLETING FORM HUD-92330, MORTGAGOR'S CERTIFICATE OF
ACTUAL COST
4-1. GENERAL INFORMATION AND DESIRED FORMAT.
A.
Heading of Form.
Self-explanatory.
B.
Columns A, B, and C in the body of the form are used to
record the actual cost of all enumerated items set
forth on the form. Blank lines are provided on the
form for listing items not provided for elsewhere.
1.
Use Column A to record those costs actually paid
in cash as of the date of the form.
2.
Use Column B to record those costs to be paid in
cash within 45 days after final endorsement.
3.
Column C is the sum of Columns A and B.
4-2. COMPLETING LINE ITEMS ON FORM HUD-92330. Use the following
guidelines to determine eligible costs for each line item.
A.
Line 1.a. Amount due under terms of Lump Sum
Construction Contract (as adjusted). Use this line if
there is no identity of interest between the
sponsor/mortgagor and the general contractor and a lump
sum construction contract is used. Enter the actual
amount of cash paid or to be paid by the mortgagor
under the terms of the construction contract as
adjusted upward or downward by the HUD estimated
cumulative effect of approved construction change
orders, liquidated/actual damages, or incentive
payment, if applicable.
1.
Recognize the HUD-estimated increase in general
requirements, if any, noted on approved time
extension change orders.
2.
Include the amount due for the cost of minor items
of on-site work which remain incomplete under the
construction contract.
3.
For capital advance and Section 8 moderate
rehabilitation programs where betterments to the
project have been added through approved change
orders, attach a breakdown of costs associated
with the betterments.
4-1
4470.2 REV-1
(4-2)
4.
Incentive.
a.
If the construction contract is modified
4/94
before initial endorsement to provide for an
incentive, compute the incentive based on the
rider attached to -the construction contract.
b.
5.
When Construction Contract Incentive Payment,
Form HUD-92443 (Form HUD-92443-CA for Section
202/811 capital advance projects), is used,
the incentive payment. is to be accounted for
on one of the blank lines on Form HUD-92330.
Damages Clause. Apply the damages clause of the
construction contract when the general contractor
doesn't complete the project by the scheduled
completion date in the construction contract as
amended by HUD change orders.
a.
b.
To determine actual damages, compute the
actual cost of interest, taxes, Insurance,
MIP and extension fees for the period from
the scheduled completion date through the
final completion date.
c.
To determine liquidated damages multiply the
daily liquidated damages rate from the
construction contract by the number of days
between the scheduled completion date and the
actual date of final completion.
d.
Prorate the net operating income for the
period of damages.
e.
B.
Calculate the amount of actual and liquidated
damages, using the lesser to determine the
adjusted upset price.
Cut the damages by the portion of the net
operating income earned during the
liquidated/ actual damage period.
Line 1.b. Amount due under terms of a Cost-Plus
Construction Contract. Use this line if there is any
identity of interest between the sponsor/mortgagor and
the general contractor or where a cost-plus form of
construction contract is used. Enter the lesser of:
1.
The cash paid or to be paid by the mortgagor.
4/94
4-2
4470.2
REV-1
(4-2)
2.
The net amount due under the terms of the
cost-plus contract, as adjusted upward or
downward by HUD's estimated cumulative effect
of approved construction changes,
liquidated/actual damages, or incentive
payment, if applicable. Refer to paragraphs
A.1 through 5.
3.
If a mortgagor acts as its own general contractor,
a construction contract is not executed. Instead,
Form HUD-92441 Supplement, is added to the
Building Loan Agreement, Form HUD-92441.
a.
b.
Incentive clause, if any, is incorporated by
addendum to Form HUD-92441 Supplement.
c.
C.
The upset price for construction is line 51
of the approved Form FHA-2328, Contractor's
and/or Mortgagor's Cost Breakdown (Schedules
of Values), as adjusted by the cumulative
effect of HUD approved change orders and the
incentive provision, if applicable.
There is no liquidated/actual damages clause.
Line 1.c. Allowable Builder's Profit.
used with line 1b only.
This line is
1.
Record builder's profit in Column C.
2.
When BSPRA is not applicable, certify to the
amount of builder's profit shown in the
construction contract whether or not it will be
paid in cash.
NOTE: The mortgagor cannot issue a residual
receipts/surplus note to evidence this debt where
the fee is not paid in cash.
D.
Lines 2.a. b and c. Architect's Fee-Design, Supervision
and Additional Services. Enter the amount paid in cash
or to be paid in cash by the mortgagor.
1.
No portion of the fee paid by means other than
cash may be considered as an allowable cost.
2.
If there is an identity of interest between the
sponsor/mortgagor and design architect, the design
fee may not exceed the amount set forth in the
Agreement and Certification, Form HUD-3305/3306.
4-3
4/94
4470.2 REV-1
(4-2)
3.
4.
Include a breakdown of any additional
services provided beyond the required basic
services.
Architects of Section 202/811 projects are not
permitted to request added monies for reimbursable
expenses and additional services beyond
compensation provided for basic services.
5.
E.
No identity of interest may exist between the
supervisory Architect and -the sponsor, mortgagor
or contractor.
Line 3. Interest during construction. Enter, the
amount of interest incurred on the HUD insured
mortgage, between initial endorsement (start of
construction for insurance upon completion projects)
and the cut-off date.
1.
Interest costs associated with an approved early
start may be allowed provided:
a.
b.
Form FHA-2415, Request for Permission to
Commence Construction Prior to Initial
Endorsement for Mortgage Insurance, was
executed and approved.
c.
2.
The certified amount, when added to the
interest cost incurred by the mortgagor, does
not exceed the total amount of interest
estimated in Section G of Form HUD-92264.
Interest cost reflects the contractor's
actual cost of money borrowed to cover the
cost of construction between the early start
date and the initial endorsement. Rate may
not exceed rate established for the insured
construction loan.
Rate paid on the construction loan cannot exceed:
a.
b.
3.
For insurance of advances -- the rate stated
in the firm commitment.
For insurance upon completion -- the rate
approved by the Director of Housing before
the start of construction.
Deduct accrued interest forgiven by the lender or
otherwise not paid in cash.
4/94
4-4
4470.2
REV-1
(4-2)
4.
5.
F.
A lender/bond underwriter's refund of any
portion of the construction loan interest
directly to the mortgagor or sponsor or on
behalf of the mortgagor to the mortgagee or
an escrow agent is not a certifiable cost.
Interest on subordinated liens or other
obligations of the mortgagor are not allowed as a
certifiable cost.
Line 4. Taxes during construction.
Based on the same
period as interest. Do not include costs accrued
during early start period.
G.
Line 5. Property Insurance.
interest.
Based on the same period as
1.
2.
H.
Include amounts for fire, windstorm, extended
coverage, liability insurance and other risk
insurance customarily insured against in the
community.
Do not include expenses incurred for workman's
compensation and public liability or costs accrued
during early start period.
Line 6. Mortgage Insurance Premiums (MIP).
same period as interest.
Based on the
1.
Insurance of advances. Enter MIP of 1/2 of 1
percent per annum on the mortgage.
2.
Insurance upon completion.
construction.
No MIP is paid during
I.
Lines 7 & 8. HUD application, commitment and inspection
fees. HUD fees are allowable in the amounts paid.
Fees paid to reopen an expired or terminated commitment
are not allowable costs.
J.
Line 9. Title and recording expense.
Enter cost of:
1.
Title search and policy at the time of initial
endorsement,
2.
Recording fees at initial endorsement,
3.
Mortgage and stamp taxes,
4.
Survey recording fees,
4-5
4470.2 REV-1
(4-2)
5.
Updating title policy during construction,
6.
7.
K.
Title search and policy and recording charges for
final endorsement, and
Legal fees incurred with any of the above.
Line 10. Allowance for Making Nonprofit Projects
Operational (AMPO) is included in the replacement cost
of insured projects involving nonprofit mortgagors
under certain Sections of the Act.
1.
Eligible costs include:
4/94
a.
Shortfalls in: interest; taxes; property
insurance premiums; mortgage insurance
premiums; ground rents and assessments during
construction when funds under the Building
Loan Agreement have been exhausted.
b.
Unforeseen costs of necessary changes
approved by the HUD Field Office.
c.
Unanticipated hard and soft costs associated
with extension of time change orders approved
by the HUD Field Office.
d.
Cost of office furniture and equipment and
lounge and lobby furniture.
e.
Cost of intangibles such as advertising and
office supplies essential to the renting of
the project.
2.
Expenditures for change orders and shortfalls in
soft costs should be certified to under those
specific line items.
3.
The amount certified to under AMPO should be the
amount of the allowance identified in Section G of
Form HUD-92264 less the amounts (change orders,
interest, taxes, etc.) certified to under other
line items.
4.
Expenses paid from the allowance are not to be
included in the operating statement.
5.
Attach to the certification, an itemization of all
expenditures covered by the allowance.
4/94
4-6
4470.2
REV-1
(4-2)
L.
6.
For Section 202/811 projects, use this line
to certify to project contingency
expenditures. Project contingency cannot be
used for intangibles or items with a short-term
life cycle such as office and
maintenance supplies.
Lines 11a-d. Financing expense. Enter the amount
incurred by the mortgagor for the initial service
charge (financing fee), construction and permanent loan
discounts, permanent marketing fees, and other similar
fees.
1.
Enter the lesser of:
a.
Amounts paid, or to be paid, in cash.
b.
2.
Amounts shown on Form HUD-2434, Mortgagee's
Certificate, or Certificate of Mortgagee
portion of Form FHA-2455 and approved by the
Field Office Director of Housing Development
before initial endorsement (insurance of
advances) and issuance of firm commitment
(insurance upon completion), respectively.
Construction lender's initial service charge (not
to exceed 2 percent):
a.
Is expected to cover:
1)
2)
"Expenses of lender's counsel."
3)
b.
"Processing fees."
All other charges by the construction
lender.
Excludes:
1)
2)
c.
Construction loan discount.
Construction loan extension fees.
Any charges made by the lender for payment of
counsel, or charges paid directly to the
lender's counsel, to the extent they cause
the initial service charge to exceed 2
percent, are not certifiable. Charges
related to "Title and Recording" expense are
certifiable under that line item.
4-7
4/94
4470.2 REV-1
(4-2)
3.
Permanent lender's placement fee (usually 1.5
percent):
a.
Is expected to cover all permanent placement
expenses except discounts and some of the
fees associated with a bond financed
transaction.
b.
If GNMA Mortgaged Backed Securities are
involved, the mortgagee may not assess an
additional charge for the MBS application fee
or for the custodial or delivery fee.
NOTE: Construction and permanent lenders' fees in
aggregate shall not exceed 3-1/2 percent and may be
divided as agreed upon by the parties involved provided
the construction lender's fee does not exceed 2
percent.
4.
Include cost of:
a.
Discounts (based upon interest rate levels at
the time of initial closing for projects
involving insurance of advances and issuance
of the firm commitment for projects involving
insurance upon completion) and construction
lender extension fees, if funded at initial
endorsement and shown on the Mortgagee's
Certificate, Form HUD-2434.
b.
Permanent lender extension fees, shown on
Form HUD-2434, if funded before the final
completion date.
c.
For insurance upon completion cases,
construction and permanent loan extension
fees, shown on the Certification of Mortgagee
portion of Form FHA-2455, if funded before
cost certification cut-off.
d.
Financing fees (including extension fees
discounts) paid on behalf of a mortgagor
third party under paragraph 18f of the
Mortgagee's Certificate or paragraph 10h
Certificate of Mortgagee portion of Form
and shown as a current liability on the
mortgagor's balance sheet.
4/94
and
by a
of
FHA-2455
4-8
4470.2
REV-1
(4-2)
e.
5.
For bond financed projects, cost of
issuance, discounts and financing fees
in excess of 3-1/2 percent provided the
information in paragraph 6-1 is
submitted.
Don't include:
a.
Any "side deals" (except for approved
discounts) by which the mortgagor agrees to
pay for "added cost of money." Any such deals
must be explained in the notes to the
financial statements.
b.
The cost of purchasing of FNMA stock.
c.
Discounts required to buy down the
construction and/or permanent rate to a below
market rate.
d.
Partial refunds of the commitment fee allowed
in processing, which are returned to the
mortgagor or sponsor.
e.
Discounts or other fees paid for by a
contribution of a portion of the initial
service charge by the lender/bond
underwriter.
M.
Lines 12 a-c.
1.
Legal, organization and audit expenses.
Organization expenses.
by the mortgagor to:
Enter the amount incurred
a.
b.
Organize a project's planning, financing and
construction,
c.
2.
Initiate a project,
Control and manage construction through
endorsement.
Legal expenses.
a.
Enter the amount incurred by the mortgagor
for: initial through final closing; tax
advice during organization of mortgagor
entity only; and preparation of documents and
representation for and during organization of
the mortgagor entity.
4-9
4/94
4470.2 REV-1
(4-2)
b.
c.
Include customary expenditures expected
to be incurred before and during initial
closing, construction period, and final
closing.
Do not include costs associated with:
1)
The usual expenses connected with land
acquisition which are already included
in, or contributing to:
a)
b)
d.
3.
Estimated market price of site.
c)
2)
Title and recording expense.
Obtaining changes in zoning.
Cost of legal services to create tax
shelters, trusts, etc.
For co-ops, see the Cooperative Housing
Handbooks 4550.1 through 4550.6 since special
instructions apply.
The audit fee covers the cost of the accountant's
audit and opinion of the mortgagor's certificate
of costs.
N.
Line 13. Other. Include all costs and recovery of
costs eligible for inclusion in the computation of the
Builder's and Sponsor's Profit and Risk Allowance
(BSPRA), which are not provided for elsewhere and which
are clearly attributable to the actual cost of the
project. These costs include:
1.
Incentive payment. based on Form HUD-92443, if
applicable.
2.
Contractor's bond premium if paid by the
mortgagor.
3.
Other fees, including engineering and
topographical survey paid by the mortgagor. If any
of these costs were included in the construction
contract, the construction contract amount must be
adjusted.
4.
Contingency reserve included in substantial
rehabilitation projects.
a.
Contingency reserve may be used for:
4/94
4-10
4470.2 REV-1
(4-2)
1)
2)
b.
Unforeseen costs of necessary
changes approved by the HUD Field
Office.
Unanticipated hard and soft costs
associated with extensions of time change
orders approved by the HUD Field Office.
Contingency reserve may not be used to:
1)
Fund changes classified as betterments by
the Field Office Architectural Branch.
2)
Provide additional profits and/ox- fees
to the architect, attorney or other
development team members.
c.
Certify expenditures for change orders and
shortfalls in soft costs under those specific
line items.
d.
Attach to the certification, an itemization of
all expenditures covered by the reserve.
O.
Subtotal.
Column C.
Self-explanatory.
Reflect the subtotal in
P.
Line 14. Builder's and Sponsor's Profit and Risk
Allowance (BSPRA). Allowed under Sections 220,
221(d)(3), 221(d)(4), and 231 of the Act if an identity
of interest exists between the a profit motivated
mortgagor and general contractor. For profit motivated
nonidentity of interest cases under these Sections of the
National Housing Act, include SPRA on this line item.
1.
BSPRA.
a.
Compute without regard to amounts on Form
HUD-92264.
1)
Use the percentage used in the original
computation of BSPRA.
2)
Base the BSPRA computation on certified
costs excluding the cost of offsites,
land, payments for acquisition of a
leasehold, ground rent, relocation
expenses, any supplemental management
fund and major moveable equipment, if
any.
4-11
4/94
4470.2 REV-1
(4-2)
b.
c.
2.
Q.
When the "50 percent: - 75 percent" rule
(refer to paragraph 5-5) is violated or
the identity of interest between the
mortgagor and general contractor ceases
to exist before final completion,
certify to SPRA on this line item. If
the "50 percent - 75 percent" rule is
violated, the general contractor
forfeits its profit.
If an identity of interest between the
mortgagor and general contractor is
established after initial endorsement and
exists at the time of final completion,
certify to BSPRA in lieu of a builder's
profit and SPRA.
SPRA. Compute based upon 10 percent of the sum of
allowed certified costs for architect's fees,
carrying charges and financing, and legal,
organizational, and audit expenses.
Line 15a-d. Consultant's Fee, Major Moveable
Equipment, Offsite and Demolition and Other.
1.
Consultant's fee. If included in the replacement
cost on Form HUD-92264 for a nonprofit mortgagor,
certify to the lesser of the amount:
a.
Paid or to be paid by the nonprofit
mortgagor.
b.
Specified in Form HUD-92531-A, Standard
Contract for Housing Consultant Services for
Nonprofit Projects Under HUD Programs
Exclusive of Section 202, or Form HUD-92531A-CA,
Contract for Housing Consultant Services
for Nonprofit Projects Under Section 202 or
Section 811, whichever is applicable.
c.
2.
Included in Form HUD-92264.
Major Moveable Equipment. When major moveable
equipment in Section 232 Nursing Home and Section
221(d) Single Room occupancy projects is not
included in the construction contract, enter the
amount expended by the mortgagor for the purchase
and installation of the equipment.
4/94
4-12
4470.2
REV-1
(4-2)
3.
a.
Contract price(s) for offsite and demolition
as adjusted by HUD's estimated cumulative
effect of approved offsite and demolition
change orders.
b.
4.
Offsite and demolition.
lesser of:
Certify to the
Actual cash paid or to be paid for offsite
and demolition work.
Other. Include all costs and recovery of costs
eligible for inclusion in the computation of
BSPRA, which are not provided for elsewhere, but
which clearly are attributable to the actual cost
of the project. These costs include:
a.
Cost of acquiring the leasehold interest.
b.
Ground rent paid during the same period used
in computing interest. Do not include costs
accrued during early start period.
c.
Residential relocation funds. Enter the
actual costs paid or to be paid by the
mortgagor for resident relocation.
d.
Supplemental management fund established on
Form HUD-92264. Certify to the full amount
identified in Section G of the Form.
R.
Subtotal.
S.
Lines 16a and b. Reflect reductions for the following:
1.
Self-explanatory.
All mortgagors, except for nonprofit mortgagors,
are required to enter the net income shown on the
operating statement accompanying the cost
certification submission.
2.
For nonprofit mortgagors, enter amount of net
income, if any, applied as an offset to
liquidated/actual damages.
3.
For co-ops, see the Cooperative Housing Handbooks
4550.1 through 4550.6 since special instructions
apply.
4.
Include the following other reductions on this
line (include an explanation of all reductions):
4-13
4/94
4470.2 REV-1
(4-2)
a.
Compensation from an insurance claim
including any income earned by investing
the proceeds of the claim.
b.
c.
T.
Refer to paragraph 6-2 for projects involving
bond financing.
Grants/loans to the mortgagor entity and/or
principals of the mortgagor entity used to
pay for any of the certified costs.
Supporting documentation.
1.
Lines 1.a. 1.b and 1.c. Attach a schedule which
identifies:
a.
The actual amount paid or to be paid under
the terms of the original contract price.
b.
Adjustment to contract price resulting from
HUD-approved change orders (Include hard
costs associated with approved time extension
change orders).
c.
Adjustment for liquidated/actual damages or
incentive payment, if applicable.
d.
Amount of any kickbacks, rebates, trade,
discounts or other similar payments received.
2.
3.
U.
Lines 2c through 6, 9 through 13 and 15b. c and d.
Provide an itemized breakdown of costs and copies
of supporting bills and receipts not submitted
previously in a draw request.
Lines 16a and b. Provide an itemized breakdown of
the indicated reductions.
Totals. This line is self-explanatory.
B will not necessarily equal Column C.
Columns A and
4/94
4-14