FRAMING CONTRACT
THIS FRAMING CONTRACT (“Contract” ), effective as of the date of the last party to sign
below, is between , having an address at
("Contractor") and , having an
address at ("Owner").
For valuable consideration the parties hereby agree as follows:
1. SCOPE OF WORK: Framing shall be to the plans including all details. Floor joist l ayout shall
be as best to avoid plumbing for tubs and toilets. Framing includes the ins tallation of sill plates;
rim joists; floor joists; sub flooring; plates; exterior and interior walls; ceiling joists; headers; rafters; r oof
sheathing; sub fascia and fascia; bridging; joist hangers; rough framing materials for stair jacks, treads and
risers; collar ties; other attic bracing materials; roof overhang and soffit; rake boards; steel and/or wood
girders; columns and posts; sill sealer under the sill plates; shea thing and siding the exterior walls; siding
corners; interior and exterior decorative beams and posts; exterior moldings; drip edge/Z-bar (including
trim materials over z-bar); windows; exterior doors (excepting the garag e door); frame and case garage
door as needed; back-out garage door as needed; ventilation materials; termite shield; furring blocks on
concrete walls; bracing; stiffbacks; backing blocks; nailing blocks; shi mming windows and doors;
caulking and gluing continuous as needed; set all finish nails; insul ation behind tubs located on exterior
walls; drywall behind tubs as required; box in vent areas; box in heat runs as required; framing for future
recessed fixtures; kitchen and bathroom cabinet drops; fire stopping as requi red; deck posts; deck girders;
deck floor joists and flooring; deck handrail and seating; deck stair j acks, treads and risers; and .
Contractor shall return all excess material and damaged materials. Contractor shall call for inspections of
the work as required.
Framing Materials:
Sill Insulation: Termite Shield:
Bridging Material: Joist Hangers:
SubFloor Material: Size: Glue:
Underlayment Material: Size: Glue:
Wall Sheathing Material: Size:
Corner Brace Material:
Wall Siding Material: Size:
Roof Sheathing Material: Size:
Flitch Plate Material/Size: Bolts:
Nails-Framing Members: Siding:
Windows: Exterior Trim: Exterior Doors:
Use Material Type Size Spacing Greatest Span
Each Size
Sill Plate N/A N/A
Box Sill/Rim Joist N/A N/A
1st Floor-Floor Joists
- 2 -
2nd Floor-Floor Joists
Ceiling Joists
Rafters/Roof Trusses
Exterior Studs
Interior Studs
Top & Bottom Plates N/A N/A
Headers, Windows & Doors N/A
Headers, Garage Door N/A
Beams N/A
Roof Bracing/Collar Ties
Exterior Trim Material Type Thickness Size
Fascia Board
Soffit
Siding Corners
Garage Door Trim
Window Trim
Door Trim
Rake Board
Exterior Beams
Exterior Posts
Flashing Material: Windows:
Doors:
Soffit Vents:
Gable Vents:
WINDOWS:
Manufacturer/Style:
Material: Insulated Glass:
Screens: Storms:
Grilles: Shutters:
STAIRS:
LOCATION JACKS TREADS RISERS
Material Size Material Size Material Size
Basement
- 3 -
1st Floor
2nd Floor
Disappearing Stairs-Make and Model Number:
EXTERIOR DOORS: (Including Storm Doors)
Door Brand/Model/Material Size Thickness Hardware
Front
Rear
Sliding/Patio
Garage
2. WORK SITE: The Project shall be constructed on the property of Owner located at
and more
particularly described as (hereafter
"the Work Site"). Owner hereby authorizes Contractor to commence and complete the usual and
customary excavation and grading on the Work Site as may be required in the judgment of the
Contractor to complete the Project. Unless called for in the drawings or specifications, no
landscaping, finish grading, filling or excavation is to be performed at the Work Site by t he
Contractor.
3. TIME OF COMPLETION: Contractor shall commence the work to be performed under this
Contract on or before and shall substantially complete the work on or before .
Contractor shall not be liable for any delay due to circumstances beyond its control including
strikes, casualty, acts of God, illness, injury, or general unavailability of mate rials.
4. PERMITS: Contractor shall apply for and obtain such permits and regulatory approvals as may
be required by the local municipal/county government, the cost thereof shal l be included as part of
the Project price.
5. INSURANCE: Contractor shall maintain general liability, workers compensation and builde r's
risk insurance.
6. SURVEY AND TITLE: If the Project is near the Owner’s property boundary, Owner will point
out property lines to the Contractor. If the Owner or Contractor has any doubt about the location
of the property lines, Owner shall provide Contractor with boundary stakes through a licensed
surveyor. In addition, Owner shall provide Contractor documentation that Owner has t itle to the
Work Site and shall provide Contractor copies of any covenants, conditions, or restrictions that
affect the Work Site.
7. CHANGES TO SCOPE OF WORK: Owner may make changes to the scope of the work,
including changes to the drawings and specifications, from time to tim e during the constr uction of
the Project. However, any such change or modification shall only be ma de by written "Change
Order" signed by both parties. Such Change Orders shall become part of this Contract. Owner
agrees to pay any increase in the cost of the Project as a result of a Change Order. In the event the
cost of a Change Order is not known at the time a Change Order is executed , the Contractor shall
estimate the cost thereof and Owner shall pay the actual cost whe ther or not it is in excess of the
- 4 -
estimated cost.
8. CONTRACT PRICE:
{COST PLUS}
Owner agrees to pay Contractor the actual cost to C ontractor of
materials plus the sum of
$ for performing the services set forth in th e
scope of the work. Contractor shall be paid as follows:
.
OR
{FIXED FEE}
Owner agrees to pay Contractor the sum of $ for performing the services set
forth in the scope of the work. Contractor shall be paid as follows:
.
Contractor shall furnish Owner appropriate releases or waivers of lien for al l work performed or
materials provided at the time the next periodic payment shall be due.
9. LATE PAYMENT/DEFAULT: A failure to make payment for a period in
excess of thirty (30) days from the due date shall be deemed a
material breach of this Contract. If payment is not made when due,
Contractor may suspend work on the job until such t ime as all
payments due have been made without breach of the C ontract pending
payment or resolution of any dispute. Owner agrees to pay a late
charge of 12% of all payments that are more than th irty (30) days
late plus interest at the rate of 12% per month.
10. DESTRUCTION AND DAMAGE : If the Project is destroyed or damaged for any reason,
except where such destruction or damage was caused by the sole negli gence of the Contractor or
its subcontractors, Owner shall pay Contractor for any additional work done by Contra ctor in
rebuilding or restoring the Project to its condition prior to such destruction or damage. If the
estimated cost of replacing work already accomplished by Contractor exc eeds 20 percent of the
Contract price, either the Contractor or Owner may terminate this Contract. Upon termination by
either party, Contractor shall be excused from further performance under this Contract and Owner
shall pay Contractor a percentage of the Contract price in proportion to the amount of work
accomplished prior to the destruction or damage.
11. ASSIGNMENT : Neither party may assign this Contract, or payments due under the Contra ct,
without the other party’s written consent. Any such assignment shall be void and of no effec t.
12. INTERPRETATION:
- 5 -
(a) Interpretation of Documents. The Contract, drawings, and specifications are intended to
supplement one another. In the event of a conflict, the specifications shall control the drawings,
and the Contract shall control both. If work is displayed on the drawings but not called for in the
sp ecifications, or if the work is called for in the specifications but not displayed on the drawings,
Contractor shall be required to perform the work as though it were called for and displayed in both
documents.
(b) Entire Agreement. This Contract constitutes the entire agreement of the parties. No other
agreements, oral or written, pertaining to the work to be performed under this Contr act exists
between the parties. This Contract may only be modified only by a writ ten agreement signed by
both parties. (c ) Governing Law. This Contract shall be interpreted and governed in accordance with the
laws of the State of Kentucky.
13. ATTORNEYS’ FEES AND COSTS: If any party to this Contract brings a cause of action
against the other party arising from or relating to this Contract, the pre vailing party in such
proceeding shall be entitled to recover reasonable attorney fees and court costs.
14. PERFORMANCE: (a) Contractor may, at its discretion, engage licensed subcontractors to perform work pursuant
this Contract provided Contractor shall remain fully responsible for the proper comple tion of the
Project. (b) All work shall be completed in a workman-like manner and in compliance w ith all
building codes and applicable laws. To the extent required by law, all work shall be performed by
individuals duly licensed and authorized by law to perform said work.
(c) Contractor agrees to remove all debris and leave the premises in broom clean condit ion.
15. WARRANTY: Contractor's warranty shall be limited to due to improper framing labor
techniques, except for the following allowances: floor variance shall not exceed 1/4 inch in 32
inches, bowed or out of plumb walls shall not exceed 1/4 inch in 32 inches, non - excessive floor
squeaks or pops. All said defects arising after one (1) year and defects in material are not
warranted by Contractor. Contractor hereby assigns to Owner all warranties on mat erials as
provided by the manufacturer of such materials.
SECTIONS 411.250 TO 411.260 OF THE KENTUCKY REVISED STATUTES
CONTAIN IMPORTANT REQUIREMENTS YOU MUST FOLLOW BEFO RE YOU MAY FILE
A LAWSUIT FOR DEFECTIVE CONSTRUCTION AGAINST THE BU ILDER OF YOUR
HOME. YOU MUST DELIVER TO THE BUILDER A WRITTEN NOT ICE OF ANY
CONSTRUCTION CONDITIONS YOU ALLEGE ARE DEFECTIVE AN D PROVIDE YOUR
BUILDER THE OPPORTUNITY TO MAKE AN OFFER TO REPAIR OR PAY FOR THE
DEFECTS. YOU ARE NOT OBLIGATED TO ACCEPT ANY OFFER MADE BY THE
BUILDER. THERE ARE STRICT DEADLINES AND PROCEDURES UNDER STATE
LAW, AND FAILURE TO FOLLOW THEM MAY AFFECT YOUR ABI LITY TO FILE A
LAWSUIT
- 6 -
AGREED:
CONTRACTOR:
Signature
Print Name & Title
Date
License Number
Name and Address of License Holder
OWNER:
Signature
Print Name
Date
- 7 -
*Optional addendum required only for home solicitat
ion sales:
BUYER'S RIGHT TO CANCEL
If this agreement was solicited to your residence a nd you do not want
the goods or services, you may cancel this agreemen t by mailing a
notice to the seller. The notice must say that you do not want the
goods or services and must be mailed before midnigh t of the third
business day after you sign this agreement. The not ice must be mailed
to:
____________________________
____________________________
____________________________
- 8 -
* Note: If this is a retail installment contract, t
he title "Retail
Installment Contract" must be added, along with the following notice,
terms, and acknowledgment of receipt:
NOTICE TO THE BUYER. DO NOT SIGN THIS CONTRACT BEFORE YOU READ IT OR IF
IT CONTAINS BLANK SPACES. YOU ARE ENTITLED TO A COPY OF THE CONTRACT
YOU SIGN.
RETAIL INSTALLMENT AGREEMENT
(No Consumer Credit Protection Act Disclosures)
Purchase Price. The total purchase price shall be $____________________________.
Interest. Interest shall be __________% simple interest per annum.
Payment Terms. Principal and interest shall be payable to Seller at ____________________________
(address), or at such other place as the holder hereof may designate in writing, in __________ consecut ive
monthly installments of $ ______________. The first of said installments shall be due and payable on t he
day of ______________, 20____, and each subsequent monthly installment shall be due and payable on
the first day of each succeeding month thereafter until the entire indebtedness i s fully paid. The maximum
number of payments is __________ .
Downpayment. The amount of to be paid upfront as downpayment is $_____________________ , to be
paid on ______________________________.
Late Fees. Purchaser shall pay Seller, or his/her assignee a late charge of ______% of any monthly
installment not received by the Seller or assignee within ______________ days after the insta llment is
due.
Purchase Money Security Interest . Seller hereby reserves and Purchaser hereby grants to Seller a
purchase money security interest in ________________________ (collateral), together with all additions,
parts, replacements, attachments, accessions, and accessories thereto and all proce eds thereof, to secure
payment of the purchase price.
Total Amount of Fees is $________________________.
Principal Balance . The amount of the sales price, total fees, minus any downpayment and the time price
differential, is $________________________.
Amount of Time Price Differential . The difference between a property's immediate purchase price and
the price the same property would cost if purchased on an installment plan is
$________________________.
Time Balance . The principal balance plus time price differential equals the sum of
$______________________ .
Buyer's acknowledgement of receipt of copy of retail installment contract:
_______________________________ ___________________________
- 9 -
Buyer's Signatu
re Date
Practical tips for completing your ‘Risers Collar Ties Other Attic Bracing Materials Roof Overhang And Soffit Rake Boards Steel Andor Wood’ online
Are you fed up with the complications of managing paperwork? Look no further than airSlate SignNow, the premier eSignature solution for individuals and small to medium-sized businesses. Bid farewell to the monotonous routine of printing and scanning documents. With airSlate SignNow, you can effortlessly fill out and sign documents online. Leverage the comprehensive features embedded in this intuitive and cost-effective platform and transform your document management practices. Whether you need to approve forms or gather eSignatures, airSlate SignNow does it all efficiently, with just a few clicks.
Follow this detailed guide:
- Log into your account or sign up for a complimentary trial of our service.
- Click +Create to upload a file from your device, cloud storage, or our template library.
- Open your ‘Risers Collar Ties Other Attic Bracing Materials Roof Overhang And Soffit Rake Boards Steel Andor Wood’ in the editor.
- Click Me (Fill Out Now) to finish the form on your part.
- Add and designate fillable fields for other participants (if necessary).
- Continue with the Send Invite settings to request eSignatures from others.
- Download, print your version, or convert it into a reusable template.
Don't worry if you need to collaborate with your team on your Risers Collar Ties Other Attic Bracing Materials Roof Overhang And Soffit Rake Boards Steel Andor Wood or send it for notarization—our solution offers everything you require to complete such tasks. Create an account with airSlate SignNow today and elevate your document management to a higher level!