5.1 Breach Of Construction Contract Claim By Contractor - Counterclaim By Owner In this case, as you know, there are several claims made by the parties
against each other, and there are a number of separate issues arising
out of those claims. These issues will be submitted to you for your
decision in the form of specific questions, known as Special
Interrogatories, which will constitute the form of your verdict. The first
claim for your consideration is the claim of the Plaintiff against the
defendant to recover sums claimed by the Plaintiff to be due and unpaid
under the contract between the parties for the construction of the
buildings and related improvements. In the case of a construction
contract, the building contractor is entitled to payment of the contract
price upon proof of "substantial performance" of the work required by
the contract. It is not necessary that the building contractor fully and
completely perform every item specified in the plans and specifications,
which are a part of the contract. The term "substantial performance"
means that degree of performance of a contract that, while not equal to
full and complete performance, is so nearly equivalent that it would be
unreasonable to deny the contractor the payment agreed upon in the
contract, subject, of course, to the owner's right to a reduction of the
contract price measured by whatever damages the owner has suffered
by reason of the contractor's failure to render full and complete
performance. Accordingly, the first two questions you will be asked (as a
part of the Special Interrogatories to be submitted to you) are:1. Do you find from a preponderance of the evidence that the Plaintiff
substantially performed its obligations under the contract (and change
orders) for the construction of the work? Answer Yes or No.2. If you answered Yes to Question One, what amount of money do you
find to be due and unpaid by the Defendant to the Plaintiff underthe contract (without reduction in amount for any damages Defendant
may have sustained due to lack of full and complete performance)?Answer in Dollars and Cents. Thus, even though you may find that the
Plaintiff substantially performed the contract, you may also find that the
Defendant nevertheless sustained damages because of a lack of full
and complete performance on the part of the Plaintiff with respect to theconstruction work. So, in that regard, the third question you will be
asked is as follows:
3. If you answered Yes to Question One, do you find from a
preponderance of the evidence that the Defendant nevertheless
sustained damages by reason of a failure on the part of the Plaintiff to
fully and completely perform the construction work? Answer Yes or No.[If you find that the Plaintiff substantially performed the construction
work, but also find that the Defendant sustained damages because of a
failure of full and complete performance by the Plaintiff, you will then
consider the issue of whether the Plaintiff, as it contends, was in fact
"prevented" by the Defendant from fully and completely performing the
work. On that issue you are instructed that, when two parties enter into
a contract, each becomes obligated under the law to permit the other to
perform the contract without interference; that is, each party must
reasonably avoid any action that would effectively hinder, obstruct or
prevent the other party from undertaking or completing whatever the
other party agreed to do.So, in this case, if you find from a preponderance of the evidence that
the Plaintiff (including the Plaintiff's subcontractors) was ready, willing
and able to perform its contractual obligations but the Defendant did
something that effectively hindered, obstructed and prevented the
Plaintiff from so doing, then the Defendant cannot recover damages forthat failure because the Defendant, personally, became charged under
the law with responsibility for it. On this issue you will be asked, as
question number four, the following:4. If you answered Yes to Question Three, do you find from a
preponderance of the evidence that the Defendant prevented the
Plaintiff from fully and completely performing the constructionwork? Answer Yes or No.] In summary, up to this point, if you find that
the Plaintiff substantially performed the construction work; and you also
find that the Defendant nevertheless sustained damages from a lack of
full and complete performance of that work[; and if you further find that
the Plaintiff was not "prevented" by any action on the part of the
Defendant from accomplishing full and complete performance of the
work], you will then consider the next issue, namely, the amount of the
damages sustained by the Defendant. Question number five, which you
will be asked concerning that issue, is as follows:5. If you answered Yes to Question Three[, and No to Question Four],
what amount of money do you find from a preponderance of the
evidence to be due to the Defendant on account of such damages,
measured by the reasonable cost in money necessary to supplyor correct the deficiencies in the Plaintiff's failure to fully and completely
perform the contract work? Answer in Dollars and Cents.The questions discussed up to this point, of course, all deal with the
issues arising out of the Plaintiff's claim against the Defendant for
alleged breach of contract resulting from the Defendant's refusal to paythe balance claimed to be due under the construction agreement.
However, the Defendant asserts a counterclaim against the Plaintiff
contending that, in fact, the Plaintiff breached the contract by failing to
substantially perform its obligations for the construction of the work. So,
if you find against the Plaintiff on its claim (answering "No" to question
number one), you will then consider question number six, as follows:6. If you answered No to Question One, do you find from a
preponderance of the evidence that the Plaintiff failed to substantially
perform its obligations under the contract (and change orders) for the
construction of the work? Answer Yes or No.If you answer "Yes" to question number six - - finding in favor of the
Defendant on the counterclaim - - you must then consider whether the
defects or omissions in the Plaintiff's performance of the work are
reasonably capable of being corrected without necessity of substantially
tearing down and completely rebuilding the improvements. If so, the
measure of the Defendant's damages under the law would be the
amount you find from a preponderance of the evidence to be the
reasonable cost of effecting those repairs or completing those
omissions. On the other hand, if you find that the defects or omissions in
the work are of such a magnitude that it would be necessary, in order to
correct them, to substantially tear down or remove the existing
improvements and rebuild them, then the cost of so doing would
obviously exceed the value that would be added to the property, and
carrying out such repairs or reconstruction would not be feasible from
an economic standpoint. Thus, under those circumstances, the measure
of the Defendant's damages under the law would not be the cost of such
reconstruction; rather, it would be the difference between the market
value of the property as actually improved by the Plaintiff, and the
market value the property would have had at the time in question if it
had been improved in compliance with the plans and specifications
incorporated in the contract. These issues will be presented to you for
resolution through the answers you supply to questions seven through
ten, as follows:7. If you answered Yes to Question Six, do you find from a
preponderance of the evidence that the defects and/or omissions in the
work are reasonably susceptible of correction and completion without
necessity of substantially tearing down and rebuilding the
improvements? Answer Yes or No.8. If you answered Yes to Question Six and Question Seven, what
amount of money do you find from a preponderance of the evidence tobe due to the Defendant as compensatory damages for the Plaintiff's
failure to substantially perform its contract for the construction of the
work, the measure of such damages being the reasonable cost in
money necessary to correct or complete the defects and/or omissions in
the construction? Answer in Dollars and Cents.9. If you answered Yes to Question Six and No to Question Seven, do
you find from a preponderance of the evidence that the defects and/or
omissions in the work are of such a character that in order to reasonablycorrect or complete them it would be necessary to substantially tear
down and rebuild the work? Answer Yes or No.10. If you answered Yes to Question Six and Question Nine, what
amount of money do you find from a preponderance of the evidence tobe due to the Defendant as compensatory damages for the Plaintiff's
failure to substantially perform its contract for the construction of the
work, the measure of such damages being the difference between the
fair market value of the defective work and the fair market value the
work would have had if properly completed in accordance with thecontract? Answer in Dollars and Cents.
5.1 Breach Of Construction Contract Claim By Contractor - Counterclaim By Owner SPECIAL INTERROGATORIES TO THE JURYDo you find from a preponderance of the evidence:1. That the Plaintiff substantially performed its obligations under the
contract (and change orders) for the construction of the work?Answer Yes or No 2. If you answered "Yes" to Question One, what amount of money do
you find to be due and unpaid by the Defendant to the Plaintiff under the
contract (without reduction in amount for any damages Defendant may
have sustained due to lack of full and complete performance)?Answer in Dollars and Cents $ 3. If you answered "Yes" to Question One, that the Defendant
nevertheless sustained damages by reason of a failure on the part of
the Plaintiff to fully and completely perform the construction work?
Answer Yes or No4. If you answered "Yes" to Question Three, that the Defendant
prevented the Plaintiff from fully and completely performing the
construction work? Answer Yes or No5. If you answered "Yes" to Question Three[, and "No" to Question
Four], what amount of money do you find from a preponderance of the
evidence to be due to the Defendant on account of such damages,
measured by the reasonable cost in money necessary to supply or
correct the deficiencies in the Plaintiff's failure to fully and completely
perform the contract work? Answer in Dollars and Cents $ 6. If you answered "No" to Question One, do you find from a
preponderance of the evidence that the Plaintiff failed to substantially
perform its obligations under the contract (and change orders) for the
construction of the work? Answer Yes or No7. If you answered "Yes" to Question Six, do you find from a
preponderance of the evidence that the defects and/or omissions in the
work are reasonably susceptible of correction and completion without
necessity of substantially tearing down and rebuilding the
improvements? Answer Yes or No8. If you answered "Yes" to Question Six and Question Seven, what
amount of money do you find from a preponderance of the evidence to
be due to the Defendant as compensatory damages for the Plaintiff's
failure to substantially perform its contract for the construction of the
work, the measure of such damages being the reasonable cost in
money necessary to correct or complete the defects and/or omissions in
the construction? Answer in Dollars and Cents $ 9. If you answered "Yes" to Question Six and "No" to Question Seven,
do you find from a preponderance of the evidence that the defects
and/or omissions in the work are of such a character that in order to
reasonably correct or complete them it would be necessary to
substantially tear down and rebuild the work? Answer Yes or No10. If you answered "Yes" to Question Six and Question Nine, what
amount of money do you find from a preponderance of the evidence to
be due to the Defendant as compensatory damages for the Plaintiff's
failure to substantially perform its contract for the construction of the
work, the measure of such damages being the difference between the
fair market value of the defective work and the fair market value the
work would have had if properly completed in accordance with the
contract? Answer in Dollars and Cents $ SO SAY WE ALL. Foreperson DATED:
Practical advice on finalizing your ‘How To Defend Against Construction Contract Violation Claims’ online
Are you weary of the difficulties of handling paperwork? Look no further than airSlate SignNow, the leading eSignature solution for individuals and businesses. Farewell to the tedious routine of printing and scanning documents. With airSlate SignNow, you can effortlessly complete and sign paperwork online. Take advantage of the powerful features included in this intuitive and economical platform and transform your strategy for paperwork management. Whether you need to approve forms or collect eSignatures, airSlate SignNow manages it all simply, needing just a few clicks.
Follow this step-by-step instructions:
- Sign in to your account or sign up for a free trial with our service.
- Click +Create to upload a document from your device, cloud, or our template collection.
- Open your ‘How To Defend Against Construction Contract Violation Claims’ in the editor.
- Click Me (Fill Out Now) to finalize the document on your part.
- Insert and designate fillable fields for others (if needed).
- Continue with the Send Invite settings to request eSignatures from others.
- Download, print your version, or convert it into a reusable template.
No need to worry if you need to collaborate with your colleagues on your How To Defend Against Construction Contract Violation Claims or send it for notarization—our platform has everything you need to complete such tasks. Enroll with airSlate SignNow today and enhance your document management to new levels!